HKSM Books Project Management with AI: From Initiation to Closing Scope Statement and Work Breakdown Structure

Scope Statement and Work Breakdown Structure

The Planning Documents

The charter told the team what the project would deliver. The scope statement and WBS tell the team exactly what that means: every deliverable broken into the discrete pieces of work that can be owned, estimated, and tracked.

Meridian Office Relocation — Project Scope Statement

The scope statement below was approved and baselined at the end of Month 1, Week 4.

DocumentProject Scope Statement
ProjectMeridian Office Relocation
PMSam Torres
PreparedMonth 1, Week 4
StatusApproved — included in baseline

In-Scope Deliverables

Six deliverables define the project's output.

# Deliverable Description Acceptance Criteria
1 Signed Westfield lease Executed lease for 80-person minimum office in Westfield District Fully executed document; rate confirmed within budget; minimum 3-year term; no terms requiring landlord approval for minor tenant changes
2 Fitted and furnished office 80 workstations; 6 enclosed meeting rooms (minimum 6-person each); building signage; access control cards for all 60 staff; lobby configuration QG-3 (Quality Gate 3) walkthrough signed by Sam Torres; zero open snag list items; all 80 workstations tested and accessible
3 Migrated IT infrastructure All servers, telephony systems, and business-critical applications operational at Westfield; data integrity confirmed; security policy compliance verified QG-4 sign-off: 2 consecutive weeks with zero critical system failures; all 5 department heads sign off
4 Completed physical move All 60 staff relocated; all company equipment and files at Westfield Zero company property remaining in current office; all staff have functional assigned workspace at Westfield by end of move week
5 Decommissioned current office Current space vacated, all company property removed, surfaces restored to lease-required condition QG-5: landlord walkthrough passed; written exit acknowledgment received from landlord
6 Staff communications program 4 all-staff messages covering: move announcement, timeline and FAQ, move logistics, post-move confirmation; FAQ intranet page live and maintained All 4 messages sent on schedule (see communications plan); FAQ updated within 48 hours of any significant change

Out of Scope

The following items were explicitly excluded from this project during scope planning, with rationale documented.

Exclusion Rationale Owner of That Work
New personal computers and peripheral hardware Standard annual IT refresh cycle applies; hardware replacement is not triggered by physical relocation Marcus Chen (IT budget)
Organizational restructuring or team reseating beyond the move HR and management decision; outside the project's mandate Elena Vasquez
Renegotiation of current office lease terms Finance team obligation handled separately before the project existed Rachel Kim (separate engagement)
New business software licenses not required by the move Separate IT annual software budget; licensing decisions follow technology strategy, not relocation Marcus Chen (IT budget)
Fit-out of landlord common areas or shared building spaces Landlord obligation per lease Not applicable
Personal items belonging to individual staff members Each staff member is responsible for personal belongings; project covers company property only Individual staff members

Project Constraints

The following constraints are non-negotiable boundaries the project must operate within.

Constraint Source Implication
Project must complete before Month 9 from charter (current lease expiry) Business case; lease agreement No milestone slippage beyond 2 weeks without emergency plan activation
Total spend may not exceed $185,000 without new executive approval Charter; finance policy PM escalates immediately if cost forecast breaches ceiling
All IT work must comply with Meridian's existing security and data policy CTO policy Marcus Chen confirms compliance at QG-2 and QG-4; any deviation requires CTO written approval
New office must have minimum 80-person seated capacity Business case requirement Lease negotiation cannot proceed on any property below this threshold

Project Assumptions

The project relies on the following facts being true. Each assumption has an owner responsible for monitoring it.

Assumption Owner Monitor At If Wrong
Westfield property available at quoted rate through letter of intent execution Rachel Kim Weeks 1-3 of Month 1 Activate backup property; notify sponsor; timeline at risk
IT systems compatible with standard commercial cabling without major remediation Marcus Chen Month 2 discovery sprint R-07 response activates; budget draw from contingency possible
Staff average productivity recovers within 10 business days post-move Priya Kapoor Week 2 post-move check Escalate to Elena Vasquez; client communications may be needed
Current landlord will release with proper written notice at lease expiry Rachel Kim Review current lease by end Month 1 Legal team engaged; costs draw from contingency; scope of R-06

Work Breakdown Structure — Meridian Office Relocation

The WBS breaks the project's six deliverables into manageable work packages. Each work package can be owned, estimated, and tracked. Activities within work packages appear in the schedule, not here. The Estimated Cost column is included because this is a worked example showing the full project picture; many organizations maintain a separate WBS for scope decomposition only and hold cost separately in the cost baseline.

WBS Code Work Package / Deliverable Owner Estimated Cost Notes
1.0 Meridian Office Relocation Project Sam Torres $185,000 Project total (base $163K + contingency $22K)
1.1 New Office Space (BRANCH) Tom Walsh $80,000
1.1.1 Site evaluation and letter of intent Priya Kapoor $5,000 Site visits, shortlisting, LOI drafted and executed
1.1.2 Lease negotiation and legal review Rachel Kim $7,000 External legal counsel; lease terms review; signature coordination
1.1.3 Office fit-out Tom Walsh $63,000 Furniture (80 workstations, 6 meeting rooms); partitions; painting; signage; access control
1.1.4 Building access and lobby configuration Tom Walsh $5,000 Access cards for all staff; lobby signage; directory
1.2 IT and Communications Infrastructure (BRANCH) Marcus Chen $45,000
1.2.1 Infrastructure design and procurement Marcus Chen $3,000 Network design; procurement list; vendor selection
1.2.2 Network cabling and hardware installation Marcus Chen $18,000 Cabling contractor; switches, routers, hardware installed at Westfield
1.2.3 Server migration and parallel run Marcus Chen $20,000 Data migration; 2-week parallel run period; cutover
1.2.4 System testing and documentation Marcus Chen $4,000 Acceptance testing; QG-4; configuration documentation
1.3 Physical Relocation (BRANCH) Priya Kapoor $18,000
1.3.1 Moving contractor selection and contract Priya Kapoor $1,500 RFQ; bid evaluation; contract signed
1.3.2 Move schedule coordination Priya Kapoor $1,500 Department-by-department move schedule; logistics planning
1.3.3 Physical move execution Priya Kapoor $14,000 Moving company contract value; all staff and equipment moved
1.3.4 Old office decommission and return Tom Walsh $1,000 Final removal; cleaning; landlord walkthrough (QG-5)
1.4 Staff Transition (BRANCH) Priya Kapoor $5,000
1.4.1 Staff communications program Priya Kapoor $2,000 4 all-staff messages; FAQ intranet page
1.4.2 Seating assignments and floor plan Priya Kapoor $1,500 Seating plan developed with department heads; floor plan finalized
1.4.3 Move-week transition support Priya Kapoor $1,500 Help desk coverage; move-day coordination; issue resolution
1.5 Project Management (BRANCH) Sam Torres $15,000
1.5.1 Project management plan Sam Torres $3,000 All subsidiary plans; governance sections; baseline lock
1.5.2 Biweekly status reporting Sam Torres $4,000 16 biweekly reports over 8 months; sponsor meetings
1.5.3 Change control management Sam Torres $2,000 Change register; review meetings; documentation
1.5.4 Project closure Sam Torres $6,000 Lessons learned facilitation; all vendor contract close-out; final report to sponsor; archive package; supplier acceptance documentation; team recognition event
Base Estimate $163,000
Contingency Reserve $22,000 Risk-based sizing (see risk register); PM authority per risk management plan
TOTAL APPROVED BUDGET $185,000

WBS Dictionary — Work Package 1.1.3

The WBS dictionary entry for WP 1.1.3, as recorded in the project management plan.

WBS Code1.1.3
Work Package NameOffice Fit-out
OwnerTom Walsh, Facilities Manager
DescriptionComplete installation of 80 workstations, 6 enclosed meeting rooms (6-person minimum each), interior partitions, wall finishes, building signage (exterior and interior), and access control system to bring the Westfield space from bare shell to occupancy-ready.
Scope BoundaryIncludes all fit-out from bare shell to occupancy-ready. Excludes: IT network cabling (WP 1.2.2), security camera systems (landlord responsibility per lease), cleaning services post-move.
Estimated Cost$63,000
Estimated Duration10 weeks (Month 3 start; Month 5 QG-3 sign-off)
Acceptance CriteriaAll 80 workstations installed and accessible; all 6 meeting rooms furnished and lockable; QG-3 walkthrough signed by Sam Torres; zero open snag list items at time of sign-off.
DependenciesWP 1.1.2 (lease executed); fit-out contractor selected (procurement activity, Month 2)
Key RisksR-03 (contractor delay), R-04 (cost overrun)

WBS Dictionary — Work Package 1.2.3

The entry for WP 1.2.3.

WBS Code1.2.3
Work Package NameServer Migration and Parallel Run
OwnerMarcus Chen, IT Lead
DescriptionMigration of all Meridian servers, telephony infrastructure, and business-critical applications from the current downtown data room to the Westfield server room, followed by a mandatory 2-week parallel run during which both environments operate simultaneously to confirm stability before the current room is decommissioned.
Scope BoundaryIncludes all server-level migration, application cutover, and parallel run operations. Excludes: end-user workstation setup (individual department responsibility post-move), new software licensing, and hardware procurement (WP 1.2.2).
Estimated Cost$20,000
Estimated Duration6 weeks (Month 6 migration start; Month 7 Week 4 QG-4 sign-off)
Acceptance CriteriaAll business systems operational for 2 consecutive weeks with zero critical failures; all 5 department heads sign the IT acceptance form (QG-4).
DependenciesWP 1.2.2 (cabling and hardware installed); WP 1.1.3 (fit-out complete so server room is accessible)
Key RisksR-02 (complexity exceeds estimate), R-07 (compatibility issues)

What's Next

With the scope defined and the WBS complete, the planning focus shifts to time, money, and people. The next chapter builds the project schedule from the WBS activities, develops the cost baseline from the work package estimates, and creates the resource plan that maps each team member's capacity against the work.

Reflect

  • The WBS assigns every work package to a single owner. WP 1.3.3 (physical move execution) is owned by Priya Kapoor, but the moving company does most of the physical work. What does it mean for Priya to "own" this work package? What specifically is she accountable for that the moving company is not?
  • The out-of-scope table includes a rationale column. Most scope conversations focus on what IS included; the rationale for exclusions matters just as much. Think of a project where something was left out of scope without a documented rationale. What risk did that create when a stakeholder later argued it should have been included?
  • WP 1.5.4 (project closure) costs $6,000 out of $15,000 in total project management. That is 40% of the PM budget. What work goes into closure that justifies that allocation? What happens on projects where closure is treated as a formality rather than a work package?

Advanced Lean Six Sigma — Data-Driven Excellence

Solve complex problems, reduce variation, and improve performance with confidence. This course is designed for professionals who already know the basics and want to apply advanced Lean Six Sigma tools to real business challenges.

This is not abstract statistics or theory-heavy training. You’ll use Excel to perform real analysis, interpret results correctly, and apply tools like DMAIC, SIPOC, MSA, hypothesis testing, and regression without memorizing formulas or relying on expensive software.

You’ll learn how to measure baseline performance, analyze process capability, use control charts to maintain stability, and validate improvements using statistical evidence. Templates, worked examples, and structured walkthroughs help you apply each concept immediately.

Learn through a complete, real-world Lean Six Sigma project and develop the skills to lead data-driven improvements with credibility. If you’re ready to move beyond basics and make decisions backed by data, enroll now and take your Lean Six Sigma expertise to the next level.



Launch your career!

HK School of Management delivers top-tier training in Project Management, Job Search Strategies, and Career Growth. For the price of a lunch, you’ll gain expert insights into landing your dream PM role, mastering interviews, and negotiating like a pro. With a 30-day money-back guarantee, there’s zero risk—just a clear path to success!

Learn More