Earned Value Analysis Results

Earned Value Analysis Results are the compiled findings from comparing planned value to value actually earned and actual cost. They include variances, performance indices, and forecasts that show cost and schedule health for a Scrum release or project. In SBOK Scrum, these results guide inspect-and-adapt decisions in reviews, retrospectives, and release planning.

Key Points

  • Output of Earned Value Analysis that consolidates PV, EV, AC, CV, SV, CPI, SPI, and forecasts such as EAC and VAC.
  • Calculated at release or project level, often mapping value to epics or user stories using story points or budgeted cost.
  • Relies on Definition of Done so only completed increments earn value.
  • Used by Product Owner and Scrum Master to re-forecast scope, schedule, and funding.
  • Feeds Scrum processes such as Demonstrate and Validate Sprint, Retrospect Sprint, and Conduct Release Planning.
  • Supports transparent stakeholder reporting with trends and threshold-based alerts.

Purpose

The purpose is to quantify how the initiative is performing versus plan in terms of cost and schedule, enabling objective, data-driven decisions. It provides early warning when delivery is off track and offers a basis to re-plan scope, budget, and timelines.

In Scrum, these results complement velocity, burn charts, and stakeholder feedback to balance value, cost, and timing while preserving agility.

Key Terms & Clauses

  • Planned Value (PV): Authorized budget or value planned to be delivered by a given date.
  • Earned Value (EV): Budgeted value of work that meets Definition of Done.
  • Actual Cost (AC): Cost actually incurred to deliver the earned value.
  • Cost Variance (CV): EV − AC; negative indicates over budget.
  • Schedule Variance (SV): EV − PV; negative indicates behind schedule.
  • Cost Performance Index (CPI): EV ÷ AC; less than 1.0 means cost inefficiency.
  • Schedule Performance Index (SPI): EV ÷ PV; less than 1.0 means schedule slippage.
  • Estimate at Completion (EAC): Forecast of total cost; common form is BAC ÷ CPI when performance is expected to continue.
  • Variance at Completion (VAC): BAC − EAC; negative suggests an overrun.
  • Baseline: Release plan scope, budget, and timing used for PV calculations.
  • Data date: The cut-off date for measurement each sprint or release checkpoint.
  • Definition of Done (DoD): Governs when EV can be claimed for a backlog item.

How to Develop/Evaluate

  • Establish a release baseline by mapping PV to epics/user stories using either story points monetized or budgeted cost per item.
  • Fix a data date (e.g., end of each sprint) and capture AC from tooling or finance.
  • Determine EV only for work that meets DoD; partial work does not earn value.
  • Compute CV, SV, CPI, SPI and produce simple trend charts across sprints.
  • Forecast EAC and VAC using agreed formulas; note assumptions behind each forecast.
  • Review thresholds (e.g., CPI or SPI < 0.9) and flag items requiring management attention.
  • Validate results with the team and Product Owner to confirm completeness and context.

How to Use

During Demonstrate and Validate Sprint, present trends to stakeholders alongside increments and burn charts to discuss scope trade-offs or funding needs. In Retrospect Sprint, analyze root causes and identify process improvements that may recover performance.

In Conduct Release Planning, use the results to update the release roadmap, adjust backlog ordering, and re-negotiate scope. For multi-team efforts, share results in Scrum of Scrums to coordinate cross-team impacts and dependencies. Update the risk register and impediment log when indicators breach agreed tolerances.

Example Snippet

By the end of Sprint 4 (data date): PV = $80,000, EV = $70,000 (only Done items), AC = $90,000.

  • CV = EV − AC = $70,000 − $90,000 = −$20,000 (over budget).
  • SV = EV − PV = $70,000 − $80,000 = −$10,000 (behind schedule).
  • CPI = EV ÷ AC = 0.78; SPI = EV ÷ PV = 0.88.
  • Assuming BAC = $200,000, EAC ≈ BAC ÷ CPI = $256,000; VAC = BAC − EAC = −$56,000.

Action: Product Owner discusses scope reduction or additional funding; Scrum Master investigates impediments and supports improvement actions in the next sprint.

Risks & Tips

  • Risk of counting partially done work; enforce DoD to avoid overstating EV.
  • Over-precision can obscure insight; keep calculations lightweight and focus on trends.
  • Story points must be consistently valued if used to derive PV/EV; avoid changing scales mid-release.
  • Do not use EVM to micromanage individuals; apply at release or team level.
  • Combine with qualitative feedback and product value metrics to avoid cost-only decisions.
  • Agree on alert thresholds and actions so teams know how results will be used.

PMP/SCRUM Example Question

During Sprint Review, the team reports CPI = 0.80 and SPI = 0.90 for the release. What is the best next step for the Product Owner?

  1. Extend the current sprint by one week to recover schedule.
  2. Update the release forecast and discuss scope trade-offs or funding options with stakeholders.
  3. Change the story point scale immediately to improve CPI and SPI.
  4. Ask the team to work overtime to increase EV next sprint without changing scope.

Correct Answer: B — Update the release forecast and discuss scope trade-offs or funding options with stakeholders.

Explanation: EVM results indicate cost and schedule pressure; the Product Owner should re-plan at the release level with stakeholders. Extending sprints, changing estimates, or mandating overtime are not aligned with Scrum and do not address the root issue.

AI for Agile Project Managers and Scrum Masters

Become an AI-first leader and transform your agile practice by leveraging artificial intelligence as your most powerful co-pilot. This course is designed to help you drive efficiency, insight, and innovation, ensuring you stay at the forefront of a rapidly evolving project management landscape.

This isn't about replacing human intuition—it's about augmenting it. You'll master prompt engineering to automate mundane tasks, freeing up your time for high-impact strategic leadership and creative problem-solving. Learn to refine backlogs, create strategic roadmaps, and integrate AI seamlessly into your agile ceremonies.

Gain predictive power by using AI-driven insights to anticipate project risks and seize new opportunities for more reliable outcomes. We deliver practical, prompt-based workflows and proven strategies built around real-world agile challenges that you can implement immediately within your framework.

Master foundational AI concepts specifically relevant to Scrum environments while developing advanced skills to handle diverse agile scenarios. You will learn to champion an AI-enabled culture within your organization, fostering a dynamic environment of continuous improvement and superior team delivery.

Ready to lead the future of agile and make data-driven decisions that cut through complexity? Join a community of forward-thinking professionals and position yourself as an indispensable leader in the AI era. Enroll now and unlock your future!



Lead with clarity, influence, and outcomes.

HK School of Management brings you a practical, no-fluff Leadership for Project Managers course—built for real projects, tight deadlines, and cross-functional teams. Learn to set direction, align stakeholders, and drive commitment without relying on title. For the price of a lunch, get proven playbooks, and downloadable templates. Backed by a 30-day money-back guarantee—zero risk, high impact.

Learn More