Trend Analysis

A technique that applies mathematical models to past performance data to predict likely future results.

Key Points

  • Looks at historical data over time to spot patterns and direction of change.
  • Uses statistical methods (e.g., regression, moving averages) to project future performance.
  • Helps forecast cost, schedule, quality, and risk metrics and supports proactive decisions.
  • Relies on consistent, accurate data and periodic review to confirm assumptions remain valid.

Example

A project manager tracks monthly CPI and SPI and fits a trendline to the last six months of data to forecast the final cost and completion date. Seeing CPI trending downward, the PM implements cost controls and negotiates scope adjustments to prevent overruns.

PMP Example Question

A PM uses a regression line on the last eight months of CPI data to predict the projects final cost. Which technique is the PM using?

  1. Parametric estimating
  2. Trend analysis
  3. Benchmarking
  4. Root cause analysis

Correct Answer: B — Trend analysis

Explanation: Trend analysis uses mathematical modeling of historical performance data (like CPI over time) to forecast future outcomes.

ICS/OT Incident Response Plan: Write One That Works

Most OT incident response plans fail before anyone writes a word: no sponsor, no charter, no agreement on who decides. This workshop course takes you from a blank page to a plan your site approves and your operators can follow.

Each of the eight sections writes one chapter of your plan: the authority and scope, the inputs, severity in the language of the plant, command and decision rights, response steps, recovery and the readiness library.

You get the plan template, more than 40 templates and worksheets, 21 worked examples and a capstone with a full model answer.

50 videos, 7.7 hours. US$147 one-time through HKSM Courses. 30-day money-back guarantee when 50% or less consumed.

Explore the Course


ICS/OT Incident Response Plan course preview

Become an AI-First Agile Leader!

HK School of Management and Technology helps you apply AI to Agile work with practical, prompt-based workflows for real-world Scrum challenges. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Learn More