Resource Leveling

A resource balancing approach that modifies the project timeline to align work with resource availability, which can shift activity dates and potentially change the critical path. Related to resource optimization techniques and resource smoothing.

Key Points

  • Used to resolve resource overallocations and conflicts by balancing demand with availability.
  • Adjusts activity start/finish dates based on resource limits; project duration may increase.
  • Can alter the critical path or create new critical paths.
  • Applied after creating a CPM schedule, especially when key resources are limited or constrained.

Example

A software project has only two senior testers, yet several testing tasks are scheduled to run at the same time. The PM levels the testers by delaying some testing activities and resequencing work, which pushes the finish date and changes the critical path but avoids overallocating the testers.

PMP Example Question

To address multiple activities competing for the same limited equipment, the PM delays some tasks and accepts a possible extension of the project duration. What technique is being used?

  1. Resource smoothing
  2. Crashing
  3. Resource leveling
  4. Fast tracking

Correct Answer: C — Resource leveling (balancing work with limited resources)

Explanation: Resource leveling adjusts the schedule to fit resource availability and can extend the timeline or change the critical path, unlike smoothing, which aims to stay within the existing dates.

Leadership for Project Managers Course

Lead with clarity, confidence, and real impact. This Leadership for Project Managers course turns day-to-day challenges—unclear priorities, tough stakeholders, and cross-functional friction—into opportunities to guide teams and deliver outcomes that matter.

You’ll learn practical leadership skills tailored to project realities: setting direction without overcontrol, creating alignment across functions, and building commitment even when authority is limited. We go beyond theory with tools you can use immediately—one-sentence visioning, stakeholder influence maps, decision framing, and feedback scripts that actually land.

Expect hands-on frameworks, real-world examples, and guided practice to prepare for tough moments—executive readouts, resistance from stakeholders, and high-stakes negotiations. Downloadable templates and checklists keep everything actionable when the pace gets intense.

Ready to influence without waiting for a bigger title? Join a community of ambitious PMs, sharpen your edge, and deliver with purpose—project after project.



Build complete project plans in minutes with AI

Stop spending hours on documentation. Learn how to use AI to create charters, WBS, schedules, risk registers, and executive reports faster—while staying fully in control. This course gives you ready-to-use prompt templates and practical workflows based on real project work. No guesswork, no fluff—just tools you can apply immediately. Backed by Udemy’s 30-day money-back guarantee, so you can start risk-free.

Learn More