Project Schedule
The schedule produced from the schedule model that shows interdependent activities with their planned dates and durations, highlights milestones, and indicates the resources assigned.
Key Points
- It is an output of the schedule model used to organize and visualize the work.
- Displays logical relationships among activities (predecessors and successors).
- Includes planned start/finish dates, durations, and key milestones.
- Shows resource assignments to activities to support execution and control.
Example
A construction project team produces a Gantt chart that links site prep to foundation work, lists planned dates and durations for each task, flags the "Foundation Complete" milestone, and identifies the crews and equipment assigned to each activity. This chart is the project schedule.
PMP Example Question
Which artifact best describes a time-phased view of logically linked activities with planned dates, durations, milestones, and assigned resources?
- Schedule baseline
- Project schedule
- Activity list
- Resource calendar
Correct Answer: B — Project schedule
Explanation: The project schedule is the output of the schedule model that presents linked activities with planned dates and durations, identifies milestones, and shows resource assignments.