Free Float

The maximum time an activity can slip without pushing the early start of any successor or breaking a schedule constraint.

Key Points

  • Free float is measured for a single activity relative to its immediate successors.
  • Computed as the earliest successor's early start minus the activity's early finish, adjusted for leads/lags and constraints.
  • If a successor is scheduled to start as soon as this activity finishes, the free float is zero.
  • Different from total float, which is based on the overall path or project finish date.

Example

Activity B finishes (EF) on day 8. Its earliest successor, Activity C, has an early start (ES) on day 10. Free float for Activity B is 2 days (10 - 8). B can be delayed up to 2 days without delaying C's early start or violating any schedule constraint.

PMP Example Question

Which statement best describes free float?

  1. The total time an activity can slip without delaying the project completion date.
  2. The time an activity can be delayed without delaying the early start of any successor or violating a schedule constraint.
  3. The slack available to the entire network path on which the activity lies.
  4. The extra time created by assigning additional resources to an activity.

Correct Answer: B — The time an activity can be delayed without pushing a successor's early start or breaking a constraint

Explanation: Free float looks only at the relationship between an activity and its successors, not the overall project finish or full path slack.

AI Systems with Claude, for Scrum Masters and Project Managers

Most AI pilots in project management do not fail on the model. They fail because somebody pointed the thing at a decision instead of at a task. This course is built around that distinction, and around the work that follows once you get it right.

Seven sections, taught against one running project from the first lecture to the last. You watch a system get built, then you build the same one against your own sprint. Nothing here is a demo that works only on the example.

You finish with five working systems and you keep them. The sprint report machine turns your board export and standup notes into the report you currently write by hand. The retro intelligence system tells you what the team keeps saying, not just what it said this time. The stakeholder comms engine drafts the update in the register the audience expects. The backlog health monitor flags the quiet decay nobody has time to check for. The risk and dependency tracker follows the chains that actually bite.

Seventy-six working files ship with it, across four sections, so every system is built against real sprint data rather than material invented for a slide. Four sprints of retrospectives, board exports, standup notes, backlog and risk data.

Explore the Course


Lead with clarity, influence, and outcomes.

HK School of Management offers a practical Leadership for Project Managers course for real projects, tight deadlines, and cross-functional teams. Learn to set direction, align stakeholders, and drive commitment without relying on title. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Learn More