Earned Value Management

A technique that integrates scope, schedule, and resource metrics to evaluate how the project is performing and progressing.

Key Points

  • Uses planned value (PV), earned value (EV), and actual cost (AC) to provide objective performance data.
  • Calculates variances and efficiency indicators (SV, CV, SPI, CPI) for early warning and control.
  • Supports forecasting of outcomes (EAC, ETC, TCPI) based on current performance trends.
  • Depends on a time-phased performance measurement baseline tied to the WBS and a defined status date.

Example

A $200,000 work package was planned to be 50% complete by week 8 (PV = $100,000). At the status date, it is 40% complete (EV = $80,000) and $110,000 has been spent (AC = $110,000). CV = EV - AC = -$30,000 (over budget), CPI = 80,000/110,000 = 0.73 (cost inefficiency), SV = EV - PV = -$20,000 (behind schedule), and SPI = 80,000/100,000 = 0.80. The project manager uses these results to adjust resources and reforecast EAC.

PMP Example Question

Which approach objectively measures performance and forecasts results by integrating scope, schedule, and cost data against a performance measurement baseline?

  1. Critical Path Method (CPM)
  2. Resource leveling
  3. Earned Value Management (EVM)
  4. Rolling wave planning

Correct Answer: C — Earned Value Management

Explanation: EVM integrates scope, schedule, and cost information to track performance and predict outcomes using metrics like PV, EV, and AC.

ICS/OT Incident Drills and Tabletop Exercises

An incident response plan is only a theory until the people who must use it have run it under pressure. This course helps OT engineers, operations leaders, IT responders, and security teams turn a plan on paper into a tested capability.

Define safe states and manual fallback before an incident forces the decision. Build escalation paths, tabletop exercises, and scenarios that expose the gaps a document review cannot find.

Then turn the results into evidence: an after-action report, owned improvements, recovery checks, and a drill cadence that keeps the program alive after the exercise ends.

51 lessons, 4.8 hours of video, eight quizzes and four hands-on assignments. US$47 one-time through HKSM Courses. 30-day money-back guarantee when 50% or less consumed.

Explore the Course


ICS/OT Incident Drills and Tabletop Exercises course preview

Build the Sprint Reporting System, Not Another Prompt

AI Systems with Claude is our own course for Scrum Masters and Agile Project Managers, taught against one running project across eight teaching sections. You build five working systems and keep them: the sprint report machine, the retro intelligence system, the stakeholder comms engine, the backlog health monitor, and the risk and dependency tracker. Direct from HK School of Management and Technology, not on Udemy.

See What Is Included