Develop Project Management Plan

The effort to design, organize, and synchronize all planning components, then merge them into one cohesive project management plan.

Key Points

  • Integrates outputs from all planning processes into a single, unified plan.
  • Results in an approved plan that includes baselines and subsidiary plans to steer execution and control.
  • Is iterative; updates are managed through integrated change control once baselined.
  • Requires coordination across teams and stakeholders to align assumptions, dependencies, and priorities.

Example

After completing the scope baseline, schedule, cost estimates, quality approach, risk responses, and communication plan, the project manager leads a workshop to resolve conflicts and align dependencies. The team consolidates these pieces into a single project management plan, secures sponsor approval, and establishes scope, schedule, and cost baselines to guide delivery.

PMP Example Question

Which activity best represents the Develop Project Management Plan process?

  1. Collecting stakeholder requirements for the product.
  2. Combining approved subsidiary plans and baselines into one document that will guide the project.
  3. Tracking schedule performance to identify variances.
  4. Determining how to acquire project team members.

Correct Answer: B — Combining approved subsidiary plans and baselines into one cohesive project management plan

Explanation: Develop Project Management Plan integrates all planning outputs into a single approved plan. The other options describe different processes.

AI for Project Managers — Build Plans Faster, Lead Better

Turn messy inputs into structured project plans in minutes. If you are a project manager tired of spending hours on documentation, this course shows you how to use AI to work faster while staying fully in control.

This is not a generic AI course. You will learn how to use AI as a practical co-pilot to build real project artifacts—charters, WBS, schedules, risk registers, and executive reports—using structured, reliable prompt frameworks.

You will also learn how to keep your project aligned across scope, schedule, cost, and risk, and how to interpret performance data like Earned Value Management to support better decisions and communication.

Everything is designed for immediate use. You get ready-to-use prompt templates and workflows you can apply right away in your projects. Watch the video to see how it works and start building your first AI-supported project plan.

Explore the Course


Take Control of Project Performance!

HK School of Management helps you go beyond status reports and gut feelings. In this advanced course, you will learn Earned Value Management (EVM) to measure progress, forecast outcomes, and take corrective action. Learn how WBS quality drives performance, how control accounts work, and how to use EAC, TCPI, and variance analysis. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Learn More