5.12 Estimate Costs

5.12 Estimate Costs
Inputs Tools & Techniques Outputs

The process of approximating the money needed to complete each activity or work package, including direct, indirect, and reserve amounts, and documenting how the numbers were developed.

Purpose & When to Use

  • Develop a realistic view of how much the project work will cost so leaders can plan funding, compare options, and set expectations early.
  • Used during planning to estimate at activity or work package level, then refined as scope, design, and quotes mature.
  • Revisited when scope changes, risks evolve, procurement information arrives, or market rates shift.
  • Outputs inform the budget baseline process and provide the basis for future cost control.

Mini Flow (How It’s Done)

  • Collect inputs: scope baseline and WBS, activity list and durations, resource needs and rates, procurement strategy and quotes, risk register, lessons learned, cost policies, taxes, and currency assumptions.
  • Select estimating approaches: analogous for quick top-down comparisons, parametric for rate-based calculations, three-point for uncertainty, and bottom-up for detailed rollups.
  • Obtain market data and vendor pricing where relevant, and analyze bids when multiple offers exist.
  • Include quality-related costs, indirects, fees, and life-cycle considerations if required by the business case.
  • Calculate activity or work package costs, document assumptions and methods, and show ranges and confidence levels.
  • Apply risk-based contingency using reserve analysis, and identify any management reserve held by sponsors if applicable.
  • Aggregate estimates to work packages and control accounts aligned to the WBS, time-phase them to the schedule, and reconcile with funding limits.
  • Produce cost estimates and a clear basis of estimate, and update the risk register and documents as needed.

Quality & Acceptance Checklist

  • Each WBS item has an estimate that matches its defined scope and resources.
  • Chosen estimating methods are appropriate for the data available and are explained clearly.
  • Rates, units, and quantities are validated, current, and sourced.
  • Assumptions, constraints, and exclusions are documented and traceable.
  • Direct, indirect, procurement, logistics, taxes, and cost of quality are considered.
  • Currency, inflation, and escalation factors are addressed when relevant.
  • Risk-based contingency is calculated and linked to specific risks; no double counting with management reserve.
  • Estimates are time-phased and consistent with the schedule.
  • Estimate ranges and confidence levels are provided where uncertainty exists.
  • Peer review completed and stakeholder acceptance recorded.

Common Mistakes & Exam Traps

  • Confusing Estimate Costs (activity-level estimating) with Determine Budget (aggregating and setting the cost baseline).
  • Providing single-point numbers without a basis, range, or confidence level.
  • Ignoring indirect costs, cost of quality, or life-cycle impacts when required.
  • Mixing up contingency (for identified risks) with management reserve (for unforeseen work).
  • Double counting reserves or applying contingency at multiple rollup levels.
  • Using analogous estimates when detailed data is available for bottom-up or parametric methods.
  • Failing to refresh estimates after design changes or new vendor quotes.
  • Choosing the lowest bid without analyzing total cost of ownership and risk.
  • Overlooking currency conversions, inflation, or timing effects on cash flow.
  • Assuming earned value techniques are used during estimating rather than during monitoring and control.

PMP Example Question

The sponsor asks for a quick cost figure early in planning to compare alternatives. Detailed design is not yet available. Which technique is most appropriate?

  1. Analogous estimating.
  2. Bottom-up estimating.
  3. Vendor bid analysis.
  4. Earned value analysis.

Correct Answer: A — Analogous estimating.

Explanation: Analogous uses historical data for fast, top-down estimates when detail is limited. Bottom-up needs detailed scope, vendor bid analysis applies to procurements, and earned value is for performance tracking, not estimating.

How To Land the Job and Interview for Project Managers Course

Take the next big step in your project management career with HK School of Management. Whether you're breaking into the field or aiming for your dream job, this course gives you the tools to stand out, impress in interviews, and secure the role you deserve.

This isn’t just another job-hunting guide—it’s a tailored roadmap for project managers. You’ll craft winning resumes, tackle tough interview questions, and plan your first 90 days with confidence. Our hands-on approach includes real-world examples, AI-powered resume hacks, and interactive exercises to sharpen your skills.

You'll navigate the hiring process like a pro, with expert insights on personal branding, salary negotiation, and career growth strategies. Plus, downloadable templates and step-by-step guidance ensure you're always prepared.

Learn from seasoned professionals and join a community of ambitious project managers. Ready to land your ideal job and thrive in your career? Enroll now and take control of your future!



Launch your career!

HK School of Management delivers top-tier training in Project Management, Job Search Strategies, and Career Growth. For the price of a lunch, you’ll gain expert insights into landing your dream PM role, mastering interviews, and negotiating like a pro. With a 30-day money-back guarantee, there’s zero risk—just a clear path to success!

Learn More