5.12 Estimate Costs

5.12 Estimate Costs
Inputs Tools & Techniques Outputs

Replace this with term.

Purpose & When to Use

  • Develop a realistic view of how much the project work will cost so leaders can plan funding, compare options, and set expectations early.
  • Used during planning to estimate at activity or work package level, then refined as scope, design, and quotes mature.
  • Revisited when scope changes, risks evolve, procurement information arrives, or market rates shift.
  • Outputs inform the budget baseline process and provide the basis for future cost control.

Mini Flow (How It’s Done)

  • Collect inputs: scope baseline and WBS, activity list and durations, resource needs and rates, procurement strategy and quotes, risk register, lessons learned, cost policies, taxes, and currency assumptions.
  • Select estimating approaches: analogous for quick top-down comparisons, parametric for rate-based calculations, three-point for uncertainty, and bottom-up for detailed rollups.
  • Obtain market data and vendor pricing where relevant, and analyze bids when multiple offers exist.
  • Include quality-related costs, indirects, fees, and life-cycle considerations if required by the business case.
  • Calculate activity or work package costs, document assumptions and methods, and show ranges and confidence levels.
  • Apply risk-based contingency using reserve analysis, and identify any management reserve held by sponsors if applicable.
  • Aggregate estimates to work packages and control accounts aligned to the WBS, time-phase them to the schedule, and reconcile with funding limits.
  • Produce cost estimates and a clear basis of estimate, and update the risk register and documents as needed.

Quality & Acceptance Checklist

  • Each WBS item has an estimate that matches its defined scope and resources.
  • Chosen estimating methods are appropriate for the data available and are explained clearly.
  • Rates, units, and quantities are validated, current, and sourced.
  • Assumptions, constraints, and exclusions are documented and traceable.
  • Direct, indirect, procurement, logistics, taxes, and cost of quality are considered.
  • Currency, inflation, and escalation factors are addressed when relevant.
  • Risk-based contingency is calculated and linked to specific risks; no double counting with management reserve.
  • Estimates are time-phased and consistent with the schedule.
  • Estimate ranges and confidence levels are provided where uncertainty exists.
  • Peer review completed and stakeholder acceptance recorded.

Common Mistakes & Exam Traps

  • Confusing Estimate Costs (activity-level estimating) with Determine Budget (aggregating and setting the cost baseline).
  • Providing single-point numbers without a basis, range, or confidence level.
  • Ignoring indirect costs, cost of quality, or life-cycle impacts when required.
  • Mixing up contingency (for identified risks) with management reserve (for unforeseen work).
  • Double counting reserves or applying contingency at multiple rollup levels.
  • Using analogous estimates when detailed data is available for bottom-up or parametric methods.
  • Failing to refresh estimates after design changes or new vendor quotes.
  • Choosing the lowest bid without analyzing total cost of ownership and risk.
  • Overlooking currency conversions, inflation, or timing effects on cash flow.
  • Assuming earned value techniques are used during estimating rather than during monitoring and control.

PMP Example Question

The sponsor asks for a quick cost figure early in planning to compare alternatives. Detailed design is not yet available. Which technique is most appropriate?

  1. Analogous estimating.
  2. Bottom-up estimating.
  3. Vendor bid analysis.
  4. Earned value analysis.

Correct Answer: A — Analogous estimating.

Explanation: Analogous uses historical data for fast, top-down estimates when detail is limited. Bottom-up needs detailed scope, vendor bid analysis applies to procurements, and earned value is for performance tracking, not estimating.

Project Management Bootcamp

Embark on a transformative journey with our Project Management Bootcamp at HK School of Management. Elevate from beginner to pro using the latest PMBOK and Process Groups Practice Guide. Our unique, engaging approach makes learning interactive and fun, replacing dull slides with dynamic doodles and real-life scenarios.

This hands-on program includes working on two full project plans. The first evolves as you learn, while the second culminates in a comprehensive plan, solidifying your expertise. You'll navigate real-world challenges, backed by quizzes and in-depth analysis, avoiding common pitfalls and setting you on a path to success.

Enhance your learning with downloadable materials and templates, invaluable for your future projects. The course covers essential topics like PMI, PMO, PMBOK, and project management ethics, delving into critical process groups and key areas such as scope, schedule, cost, and stakeholder management.

Learn from seasoned professionals and join a community of enthusiastic lifelong learners. Ready to master project management and lead with confidence? Enroll now and start your transformation!



Stop Managing Admin. Start Leading the Future!

HK School of Management helps you master AI-Prompt Engineering to automate chaos and drive strategic value. Move beyond status reports and risk logs by turning AI into your most capable assistant. Learn the core elements of prompt engineering to save hours every week and focus on high-value leadership. For the price of lunch, you get practical frameworks to future-proof your career and solve the blank page problem immediately. Backed by a 30-day money-back guarantee-zero risk, real impact.

Enroll Now
``` ### Marketing Notes for this Revision: * **The Hook:** I used the "Stop/Start" phrasing from your landing page description because it creates a clear transformation for the user. * **The Value:** It highlights the specific pain point mentioned in your text (drowning in administrative work) and offers the "AI Assistant" model as the solution. * **The Pricing/Risk:** I kept the "price of lunch" and "guarantee" messaging as it is a powerful way to reduce friction for a Udemy course. Would you like me to create a second version that focuses more specifically on the "fear of obsolescence" mentioned in your landing page info?