Resources requirements
A structured statement of the types, quantities, skills, and timing of people, equipment, materials, and facilities needed to perform project work. It is typically time-phased and supports schedule, cost, and procurement planning.
Key Points
- Describes what resources are needed, in what quantities, and when they are required across the life of the project.
- Covers labor and non-labor resources such as team roles, equipment, materials, supplies, and facilities.
- Expresses needs in measurable units (for example, person-hours, FTEs, quantity, capacity) and is often time-phased.
- Informs staffing plans, cost estimates, procurement strategy, and resource leveling or smoothing.
- Is developed iteratively and updated as scope, schedule, risks, and constraints evolve.
- Should include the basis of estimate, assumptions, and constraints for traceability and decision-making.
Purpose of Analysis
- Translate the scope and activity work into specific, quantifiable resource needs to enable feasible planning.
- Align demand for people and assets with availability, calendars, and organizational or vendor constraints.
- Provide inputs to cost and schedule models, including resource-driven durations and time-phased budgets.
- Surface risks, dependencies, and procurement lead times early to reduce later delays and rework.
Method Steps
- Review scope, WBS, and activity list to identify the work that drives resource demand.
- Classify required resources by type (people, equipment, materials, facilities) and by role or specification.
- Estimate quantities and effort using expert judgment, analogous, parametric, or bottom-up techniques.
- Apply calendars and availability to convert effort into capacity needs (for example, FTEs per period) and time-phase the demand.
- Validate practicality with resource owners or vendors; consider make-or-buy and skill availability.
- Document the basis of estimates, assumptions, and constraints; capture risks and issues found.
- Consolidate into a resource requirements list and, if useful, a resource breakdown structure and histogram.
- Integrate with schedule and cost planning; iterate as plans are adjusted or risks materialize.
Inputs Needed
- Scope baseline, WBS, and activity list with attributes.
- Resource calendars, organizational policies, skill catalogs, and role descriptions.
- Historical data, lessons learned, and reference class benchmarks.
- Cost rates, vendor catalogs, and procurement strategy or contracts.
- Assumptions log, constraints, risk register, and stakeholder requirements.
Outputs Produced
- Documented resource requirements by activity or work package, time-phased where applicable.
- Role descriptions or skill requirements and quantity takeoffs for materials and equipment.
- Resource breakdown structure and resource histograms or demand profiles.
- Basis of estimate and updates to the assumptions log and risk register.
- Inputs to staffing management, procurement planning, schedule development, and cost estimating.
Interpretation Tips
- Differentiate effort from duration; availability and calendars determine how effort translates into time.
- Use generic roles early (for example, Senior Analyst) and assign named individuals later to maintain flexibility.
- For non-labor items, specify quantity, performance specs, and lead times to support procurement and logistics.
- Check for peaks in demand; plan resource leveling or staged deliveries to avoid overloads and idle time.
- Validate with resource owners and vendors to confirm feasibility and identify constraints or alternatives.
Example
For a 12-week initiative, the team analyzes each work package and derives the following time-phased needs:
- Analysis: 2 Business Analyst FTEs for weeks 1-4; 1 Architect at 50% for weeks 2-3.
- Build: 3 Specialist FTEs for weeks 5-9; 1 test environment for weeks 6-10; 200 units of consumables by week 5.
- Pilot and rollout: 1 Trainer FTE for weeks 10-12; 10 loaner devices for week 11; a training room for 3 days.
These requirements feed the staffing plan, reserve the environment, and trigger a purchase order for consumables with a 3-week lead time.
Pitfalls
- Listing headcount without units or time-phasing, making integration with schedule and cost unreliable.
- Ignoring calendars, lead times, or onboarding time, which inflates risk of delays.
- Underestimating non-labor resources (facilities, licenses, materials) and focusing only on people.
- Failing to capture the basis of estimate, hindering future refinement and stakeholder trust.
- Double-counting shared resources across activities or not accounting for multitasking limits.
- Skipping validation with resource owners or vendors, leading to infeasible plans.
PMP Example Question
While estimating resource requirements for each activity, the team needs to express labor needs in a way that supports scheduling and cost estimating. What is the best practice?
- Record headcount by name for the entire project duration.
- Document effort and capacity using units such as person-hours or FTEs and time-phase them.
- Estimate only critical path activities since noncritical work can be adjusted later.
- Defer non-labor resources to procurement planning.
Correct Answer: B — Document effort and capacity using units such as person-hours or FTEs and time-phase them.
Explanation: Quantified, time-phased requirements integrate cleanly with calendars, cost rates, and scheduling. The other options reduce accuracy or delay important planning for non-labor needs.
HKSM