Three-point estimating

An estimating technique that uses three inputs—optimistic, most likely, and pessimistic—to calculate an expected value and a range for duration or cost. It captures uncertainty and supports risk-aware planning and communication.

Key Points

  • Uses optimistic (O), most likely (M), and pessimistic (P) values to model uncertainty.
  • Common formulas: triangular mean (O + M + P) / 3 and beta/PERT mean (O + 4M + P) / 6.
  • Standard deviation often approximated as (P - O) / 6 for beta/PERT to express variability.
  • Applies to duration, cost, or effort at activity, work package, or feature level.
  • Improves stakeholder communication by providing an expected value with a range and confidence.
  • Relies on expert judgment and historical data; assumptions must be documented.

When to Use

  • When scope is understood but uncertainty in effort, cost, or duration remains.
  • When risks could realistically push outcomes higher or lower than the most likely value.
  • When stakeholders need a range and confidence level rather than a single point.
  • During early planning to set realistic expectations and during re-estimation as new data emerges.
  • When combining with quantitative risk analysis or Monte Carlo simulations.

How to Estimate

  • Define the item to estimate and the unit of measure (e.g., days, hours, currency).
  • Elicit O, M, and P from qualified estimators, using historical data and clear assumptions.
  • Select a distribution: triangular for simple averaging; beta/PERT for a weighted mean toward M.
  • Calculate expected value: triangular = (O + M + P) / 3; beta/PERT = (O + 4M + P) / 6.
  • Estimate variability: standard deviation ≈ (P - O) / 6 (beta/PERT); compute variance as SD².
  • Derive a range or confidence interval (e.g., expected ± 1 or 2 standard deviations).
  • Review with the team, validate assumptions, and adjust for known correlations or constraints.
  • Document the basis of estimate and update the assumptions log and risk register.

Inputs Needed

  • Defined scope, WBS, and activity or work package descriptions.
  • Historical data or reference class data for similar work.
  • Expert judgment from people who will perform or have performed the work.
  • Risk register entries relevant to the item being estimated.
  • Resource calendars, availability, and productivity assumptions.
  • Organizational estimating policies, units, and calendars.
  • Assumptions and constraints that affect optimistic or pessimistic conditions.

Outputs Produced

  • Expected value estimate for duration or cost.
  • Range expressed via optimistic and pessimistic bounds and, optionally, a confidence interval.
  • Standard deviation and variance for the estimate, where applicable.
  • Basis of estimates documenting data sources, assumptions, and methods used.
  • Updates to the assumptions log and risk register based on insights from O and P scenarios.

Assumptions

  • Optimistic and pessimistic values are feasible and reflect realistic conditions.
  • The chosen distribution shape reasonably represents uncertainty for the item.
  • Units, calendars, and productivity rates are consistent across O, M, and P.
  • Correlations with other estimates are recognized and handled during aggregation.
  • O and P consider identified risks and opportunities but exclude unknown unknowns.

Example

You are estimating the duration of an activity with O = 8 days, M = 10 days, and P = 16 days.

  • Triangular mean = (8 + 10 + 16) / 3 = 11.33 days.
  • Beta/PERT mean = (8 + 4 × 10 + 16) / 6 = 10.67 days.
  • Standard deviation (beta/PERT) ≈ (16 - 8) / 6 = 1.33 days; variance ≈ 1.78 days².
  • Approximate 95% range ≈ 10.67 ± 2 × 1.33 = 8.01 to 13.33 days.

Report the expected value with the range and document the assumptions behind O and P.

Pitfalls

  • Using unrealistic O or P values that are not actually achievable.
  • Anchoring on the most likely value and ignoring the calculated range.
  • Mixing units or calendars across estimates, which distorts results.
  • Ignoring dependencies and correlations when aggregating multiple estimates.
  • Overstating precision by reporting too many decimal places.
  • Failing to update estimates as new information and performance data emerge.

PMP Example Question

A team wants to reflect uncertainty in activity duration estimates and provide stakeholders with an expected value and a realistic range. Which technique should the project manager recommend?

  1. Analogous estimating
  2. Bottom-up estimating
  3. Three-point estimating
  4. Parametric estimating

Correct Answer: C — Three-point estimating.

Explanation: Three-point estimating uses optimistic, most likely, and pessimistic values to produce an expected value and a range, making uncertainty explicit.

How To Land the Job and Interview for Project Managers Course

Take the next big step in your project management career with HK School of Management. Whether you're breaking into the field or aiming for your dream job, this course gives you the tools to stand out, impress in interviews, and secure the role you deserve.

This isn’t just another job-hunting guide—it’s a tailored roadmap for project managers. You’ll craft winning resumes, tackle tough interview questions, and plan your first 90 days with confidence. Our hands-on approach includes real-world examples, AI-powered resume hacks, and interactive exercises to sharpen your skills.

You'll navigate the hiring process like a pro, with expert insights on personal branding, salary negotiation, and career growth strategies. Plus, downloadable templates and step-by-step guidance ensure you're always prepared.

Learn from seasoned professionals and join a community of ambitious project managers. Ready to land your ideal job and thrive in your career? Enroll now and take control of your future!



Launch your career!

HK School of Management delivers top-tier training in Project Management, Job Search Strategies, and Career Growth. For the price of a lunch, you’ll gain expert insights into landing your dream PM role, mastering interviews, and negotiating like a pro. With a 30-day money-back guarantee, there’s zero risk—just a clear path to success!

Learn More