Project schedule

A project schedule is a time-phased plan that maps activities, durations, dependencies, milestones, and dates. It guides execution and control by showing when work starts and finishes and how changes affect the overall timeline.

Key Points

  • The schedule is a model of how the project timeline will unfold, not just a calendar of tasks.
  • Critical and near-critical paths reveal where delays will directly impact the finish date.
  • Float (slack) indicates schedule flexibility and opportunities for sequencing choices.
  • Resource availability and calendars can change the critical path after leveling.
  • Regular updates with actuals enable forecasting and timely corrective actions.
  • Scenario testing (what-if, fast-tracking, crashing) supports informed trade-off decisions.

Purpose of Analysis

  • Assess feasibility of the planned finish date and major milestones.
  • Identify critical and near-critical paths and the drivers of the completion date.
  • Reveal schedule risks, long-lead items, and activities with low float.
  • Evaluate the effect of resource limits and calendars on timelines.
  • Support decision-making on compression, sequencing, and risk responses.

Method Steps

  • Validate activity list, dependencies, and calendars for complete and correct logic.
  • Confirm duration estimates and resource assignments for each activity.
  • Run critical path calculations to determine path(s) with zero or minimal float.
  • Check for over-allocation and perform resource leveling, then recalc paths and float.
  • Analyze constraints, lags, and leads; remove unnecessary hard dates and weak logic.
  • Conduct what-if analysis for compression options (fast-tracking, crashing) and risks.
  • Establish or update the schedule baseline and define the update cycle and forecasting approach.

Inputs Needed

  • Scope breakdown (WBS), activity list, and defined dependencies.
  • Duration estimates, resource assignments, and resource calendars.
  • Project calendar(s), constraints, assumptions, and milestones.
  • Risk register items that affect time (e.g., uncertainty, long-lead risks).
  • Organizational policies, tools, and scheduling method rules.
  • Actual start/finish dates and progress data for updates and forecasts.

Outputs Produced

  • Updated schedule model with dates, critical path(s), and float values.
  • Schedule baseline and milestone list with target dates.
  • Resource profiles and histograms after leveling.
  • What-if scenarios and recommended compression or sequencing changes.
  • Forecasts (revised finish date, milestone slippage) and performance indicators.
  • Assumptions and risks specific to the schedule, including buffers or contingency time.

Interpretation Tips

  • Look beyond the final date; inspect the drivers and relationships on critical and near-critical paths.
  • Check float distribution; multiple near-critical paths mean higher schedule risk.
  • After leveling, recheck which path is critical; resources can change the driver.
  • Watch for hard date constraints that hide real risk; prefer logic-driven sequencing.
  • Validate that leads/lags reflect real work, not placeholders for missing tasks.
  • Use ranges or buffers when uncertainty is high instead of single-point optimism.

Example

A mid-size project creates a network of 120 activities with resource assignments. The team runs a critical path analysis and finds two near-critical paths within three days of the critical path. After leveling resources, the critical path shifts because a key specialist is over-allocated. The team tests fast-tracking two design-review handoffs and adds a small buffer to protect a long-lead procurement. The updated schedule baseline meets the target date with identified risks and monitoring points.

Pitfalls

  • Building the schedule around fixed dates instead of sound dependency logic.
  • Ignoring resource limits, leading to unrealistic timelines that fail in execution.
  • Underestimating durations and removing all float, leaving no resilience.
  • Overusing leads/lags to mask missing detail or poor sequencing.
  • Failing to update actuals regularly, making forecasts unreliable.
  • Focusing only on the critical path and overlooking near-critical risks.
  • Using a level of detail that is too coarse or too granular to manage effectively.

PMP Example Question

The sponsor asks to pull in the delivery date by 10 days. What should the project manager do first when analyzing the project schedule?

  1. Crash all activities by 10% across the schedule.
  2. Evaluate fast-tracking and crashing options on the current critical path.
  3. Compress activities with the largest float to free up time.
  4. Extend the workweek by adding weekend work for the entire team.

Correct Answer: B — Evaluate fast-tracking and crashing options on the current critical path.

Explanation: Compression decisions should target the critical path first and be evaluated for impact and risk before implementation. Compressing noncritical work or making blanket changes may not improve the finish date and can add risk.

How To Land the Job and Interview for Project Managers Course

Take the next big step in your project management career with HK School of Management. Whether you're breaking into the field or aiming for your dream job, this course gives you the tools to stand out, impress in interviews, and secure the role you deserve.

This isn’t just another job-hunting guide—it’s a tailored roadmap for project managers. You’ll craft winning resumes, tackle tough interview questions, and plan your first 90 days with confidence. Our hands-on approach includes real-world examples, AI-powered resume hacks, and interactive exercises to sharpen your skills.

You'll navigate the hiring process like a pro, with expert insights on personal branding, salary negotiation, and career growth strategies. Plus, downloadable templates and step-by-step guidance ensure you're always prepared.

Learn from seasoned professionals and join a community of ambitious project managers. Ready to land your ideal job and thrive in your career? Enroll now and take control of your future!



Launch your career!

HK School of Management delivers top-tier training in Project Management, Job Search Strategies, and Career Growth. For the price of a lunch, you’ll gain expert insights into landing your dream PM role, mastering interviews, and negotiating like a pro. With a 30-day money-back guarantee, there’s zero risk—just a clear path to success!

Learn More