7.7 Control Quality

7.7 Control Quality
Inputs Tools & Techniques Outputs

Replace this with term.

Purpose & When to Use

Control Quality confirms that project outputs meet specified requirements. It uses inspection, measurement, and testing to find defects, verify fixes, and provide objective evidence of conformance. Use it throughout delivery, especially when work packages complete, before handing items to customer acceptance.

Mini Flow (How It’s Done)

  • Prepare: gather quality metrics, acceptance criteria, sampling plan, and test procedures.
  • Inspect and test: perform checks, measurements, or trials on work results and deliverables.
  • Record findings: log defects, variances, and measurement data using checklists or check sheets.
  • Analyze: use basic statistics and charts to spot trends, outliers, and root causes.
  • Correct and re-test: request rework, verify fixes, and confirm compliance with metrics.
  • Output and communicate: produce verified deliverables, measurement results, change requests, and updates to plans and lessons learned.

Quality & Acceptance Checklist

  • Applicable quality metrics and tolerances are identified and current.
  • Test or inspection methods are defined, repeatable, and tools are calibrated.
  • Sampling approach and acceptance criteria are documented and followed.
  • All checks are executed; results and evidence are recorded and traceable.
  • Defects are logged with severity, location, and responsible owner.
  • Rework is completed and verified; failed items are not released.
  • Recurring or systemic issues undergo root cause analysis and actions are captured.
  • Configuration item identity matches the version tested and approved.
  • Verified deliverables and measurement summaries are prepared for customer acceptance.
  • Change requests, updates to the quality plan, and lessons learned are submitted as needed.

Common Mistakes & Exam Traps

  • Mixing up Control Quality and Validate Scope: Control Quality is internal conformance checks; Validate Scope is customer or sponsor acceptance.
  • Confusing Manage Quality with Control Quality: Manage Quality improves the process and plans; Control Quality measures outputs and finds defects.
  • Relying on 100% inspection when statistical sampling would be sufficient and cost-effective.
  • Ignoring trends or special-cause variation on charts; passing items that show unstable process behavior.
  • Failing to submit change requests for preventive or corrective actions discovered during testing.
  • Not keeping objective evidence (records, logs, measurements), which weakens acceptance and audits.
  • Skipping re-verification after rework or not updating configuration status.

PMP Example Question

You completed inspections on a deliverable, logged defects, and after rework it meets all specified metrics. What should you hand off next for formal acceptance?

  1. Approved change requests.
  2. Verified deliverable and measurement results.
  3. Updated risk register.
  4. Lessons learned updates.

Correct Answer: B — Verified deliverable and measurement results.

Explanation: Control Quality produces verified deliverables and objective evidence of conformance, which are then presented in Validate Scope for formal acceptance.

Advanced Project Management — Measuring Project Performance

Move beyond guesswork and status reporting. This course helps you measure real progress, spot problems early, and make confident decisions using proven project performance techniques. If you manage complex projects and want clearer visibility and control, this course is built for you.

This is not abstract theory. You’ll work step by step through Earned Value Management (EVM), learning how cost, schedule, and scope come together to show true performance. You’ll build a solid foundation in EVM concepts, understand why formulas work, and learn how performance data actually supports leadership decisions.

You’ll master Work Breakdown Structures (WBS), control accounts, and budget baselines, then apply core EVM metrics like EAC, TCPI, and variance analysis. Through a detailed real-world example, you’ll forecast outcomes, analyze trends, and understand contingencies and management reserves with confidence.

Learn how experienced project managers monitor performance, communicate results clearly, and take corrective action before projects slip. With practical exercises and hands-on analysis, you’ll be ready to apply EVM immediately. Enroll now and start managing performance with clarity and control.



Lead with clarity, influence, and outcomes.

HK School of Management brings you a practical, no-fluff Leadership for Project Managers course—built for real projects, tight deadlines, and cross-functional teams. Learn to set direction, align stakeholders, and drive commitment without relying on title. For the price of a lunch, get proven playbooks, and downloadable templates. Backed by a 30-day money-back guarantee—zero risk, high impact.

Learn More