Approved change requests
Approved change requests are formal authorizations to implement specific changes to project baselines, plans, deliverables, or documents after evaluation by a defined change authority. They specify what will change, when it takes effect, and any conditions for implementation.
Key Points
- Approved change requests document authorized modifications and the decision that allowed them.
- They result from the project's change control process and are inputs to implementing and controlling work.
- Each approval should state scope of change, impacts, constraints, and effective date.
- Traceability is required from the original request through analysis, decision, implementation, and verification.
- They may trigger updates to baselines, plans, contracts, and configuration items.
- In adaptive approaches, approvals can be delegated (e.g., product owner), and prioritized backlog items serve as authorization within governance limits.
Purpose
To provide clear, auditable authorization to modify project work in a controlled manner. This artifact prevents scope creep, aligns stakeholders on what will change and why, and enables consistent implementation, monitoring, and verification.
Who Approves
- Change control board (CCB) for changes that affect baselines or major constraints, as defined in the change management plan.
- Project sponsor for strategic, funding, or scope decisions beyond the CCB's authority.
- Product owner in adaptive approaches for product backlog content and priority within agreed guardrails.
- Project manager for low-impact changes within documented tolerances and delegations.
- Functional managers or resource owners for staffing changes within their allocation authority.
- Procurement/contract authority for vendor-related changes requiring contract amendments.
How to Prepare
- Reference the original change request ID and link to the analysis and decision record (approver, date, outcome).
- Describe the approved change clearly: what is changing, why, scope boundaries, and conditions or constraints.
- Summarize impact analysis results across scope, schedule, cost, quality, risks, value, and stakeholder impact.
- List affected baselines, plans, documents, and configuration items, including new version identifiers.
- Define the implementation approach: tasks, owner, start date, dependencies, rollout steps, and rollback/contingency.
- Specify acceptance criteria, verification method, and how completion will be evidenced and closed in the log.
- Outline communication, training, and procurement actions (e.g., change orders) if applicable.
How to Use
- Update relevant baselines and management plans per the approval and configuration management rules.
- Create or update schedule activities or backlog items, assign owners, and integrate into current iteration or release as appropriate.
- Coordinate with vendors and issue contract change orders when required by procurement terms.
- Communicate the change to affected stakeholders and team members; maintain traceability in the change log.
- Monitor implementation through Direct and Manage Project Work and verify outcomes through quality control.
- Update risks, assumptions, and lessons learned; close the change in the log after verification.
Gate Checklist Example
- Approval recorded with authority, date, and any conditions or limits.
- Baseline and plan updates drafted, reviewed, and versioned in the configuration system.
- Schedule integrated and dependencies analyzed; no conflicts with critical milestones.
- Funding confirmed and cost baseline updated; benefits case still valid.
- Quality and acceptance criteria defined; test or validation plan prepared.
- Risks, communications, and training updates complete; owners assigned.
- Rollback/contingency plan defined and feasible.
- Regulatory, compliance, or cybersecurity impacts assessed and approvals obtained if needed.
- For procurements, contract change order prepared and supplier acknowledgment planned.
Governance Rules
- Define thresholds and delegated authority levels for different change types and impacts.
- Maintain a single change log and configuration management system as the system of record.
- No implementation without recorded approval, except via documented emergency procedures.
- Time-box decisions and set approval expiry if not implemented by a stated date.
- Ensure segregation of duties between requester, analyst, approver, and implementer where practical.
- Retain complete audit trails, including alternatives considered and rationale for the decision.
- Establish change freeze windows and exceptions criteria for critical phases or releases.
PMP Example Question
A change request has been reviewed and approved by the change control board. What should the project manager do next?
- Update the schedule and implement the change immediately without further actions.
- Communicate the approval, update baselines and plans as needed, create implementation tasks, and track execution.
- Reopen impact analysis to confirm the original assumptions before acting.
- Log the approval and defer implementation to project closeout.
Correct Answer: B — Communicate the approval, update baselines and plans, create tasks, and track execution.
Explanation: Once a change is approved, it is integrated into the project and implemented under controlled execution, followed by verification. Reanalysis or deferral is not appropriate unless conditions have changed.
HKSM