5.9 Estimate Activity Durations

5.9 Estimate Activity Durations
Inputs Tools & Techniques Outputs

Replace this with term.

Purpose & When to Use

  • Determine how much time each defined activity needs to be completed under expected conditions.
  • Used during planning after activities and resources are identified, and revisited whenever scope, resources, or risks change.
  • Feeds the schedule model, critical path analysis, milestones, and time-related risk and cost decisions.
  • Improves predictability by making assumptions, constraints, and uncertainty visible.

Mini Flow (How It’s Done)

  • Review inputs: activity list and attributes, resource needs and assignments, calendars, scope details, assumptions, risks, and historical data.
  • Engage estimators: involve the people who will do the work, relevant experts, and suppliers to validate approach and rates.
  • Select techniques: use analogous (by comparison), parametric (rates × quantities), three‑point (optimistic, most likely, pessimistic), bottom‑up (roll up from detailed tasks), and reserve analysis as appropriate.
  • Consider drivers: resource availability and skill, productivity, learning curve, work windows, dependencies, constraints, tools, quality standards, and known risks.
  • Calculate durations: apply chosen methods, convert to working time using calendars, and where using three‑point, compute an expected value and a range.
  • Assess uncertainty: add time contingency for known risks in activities or as task buffers; keep any management reserve separate from the baseline.
  • Document the basis: sources, assumptions, methods, ranges, confidence level, and key constraints for each estimate.
  • Update records: revise activity attributes, risk and assumptions logs, lessons learned, and schedule data; share for review and agreement.

Quality & Acceptance Checklist

  • Each activity has a duration in working time units and aligns with the defined scope.
  • Assumptions and constraints affecting time are clearly documented.
  • Estimation method used and data sources are recorded and traceable.
  • Resource calendars, availability, and skill levels are reflected in the numbers.
  • Uncertainty is expressed as ranges and/or confidence levels; risk‑based contingency is visible, not hidden.
  • Dependencies, leads, and lags are explicit and justifiable.
  • Estimates are reviewed by the people doing the work and relevant experts.
  • Units are consistent across all activities and milestones.
  • The basis of estimates is stored for future updates and audits.
  • Updates are triggered when scope, resources, or risk responses change.

Common Mistakes & Exam Traps

  • Confusing effort (person‑hours) with duration (elapsed time), especially when resource availability is part‑time.
  • Ignoring calendars and resource constraints, leading to calendar‑day estimates instead of working‑day estimates.
  • Using analogous estimates when projects are not truly comparable, or parametric rates without validated productivity data.
  • Providing single‑point numbers with no ranges or risk consideration, or hiding padding instead of using transparent contingency.
  • Estimating without involving those who will perform the work, increasing optimism bias.
  • Failing to update durations after approved scope changes or risk responses like crashing or fast tracking.
  • Assuming adding people will always shorten duration, ignoring coordination overhead and task type.
  • Misusing leads and lags to mask schedule problems rather than modeling real dependencies.

PMP Example Question

A specialist needed for a critical activity will be available only 50% next month. The team previously estimated the activity as 40 hours of effort over one week. What should the project manager do to improve the duration estimate?

  1. Add a management reserve to the schedule to cover the risk.
  2. Apply the resource calendar and re‑estimate duration based on 50% availability.
  3. Add more people to the activity to keep the one‑week duration.
  4. Ask the sponsor to confirm the one‑week deadline.

Correct Answer: B — Apply the resource calendar and re‑estimate duration based on 50% availability.

Explanation: Duration depends on resource availability. With half‑time availability, 40 hours of effort will span about two weeks of elapsed time, assuming no other constraints.

Advanced Project Management — Measuring Project Performance

Move beyond guesswork and status reporting. This course helps you measure real progress, spot problems early, and make confident decisions using proven project performance techniques. If you manage complex projects and want clearer visibility and control, this course is built for you.

This is not abstract theory. You’ll work step by step through Earned Value Management (EVM), learning how cost, schedule, and scope come together to show true performance. You’ll build a solid foundation in EVM concepts, understand why formulas work, and learn how performance data actually supports leadership decisions.

You’ll master Work Breakdown Structures (WBS), control accounts, and budget baselines, then apply core EVM metrics like EAC, TCPI, and variance analysis. Through a detailed real-world example, you’ll forecast outcomes, analyze trends, and understand contingencies and management reserves with confidence.

Learn how experienced project managers monitor performance, communicate results clearly, and take corrective action before projects slip. With practical exercises and hands-on analysis, you’ll be ready to apply EVM immediately. Enroll now and start managing performance with clarity and control.



Launch your career!

HK School of Management provides world-class training in Project Management, Lean Six Sigma, and Agile Methodologies. Just for the price of a lunch you can transform your career, and reach new heights. With 30 days money-back guarantee, there is no risk.

Learn More