5.9 Estimate Activity Durations
Forecast how long each activity will take based on scope, resources, methods, and constraints so a realistic schedule can be built and maintained.
Purpose & When to Use
- Determine how much time each defined activity needs to be completed under expected conditions.
- Used during planning after activities and resources are identified, and revisited whenever scope, resources, or risks change.
- Feeds the schedule model, critical path analysis, milestones, and time-related risk and cost decisions.
- Improves predictability by making assumptions, constraints, and uncertainty visible.
Mini Flow (How It’s Done)
- Review inputs: activity list and attributes, resource needs and assignments, calendars, scope details, assumptions, risks, and historical data.
- Engage estimators: involve the people who will do the work, relevant experts, and suppliers to validate approach and rates.
- Select techniques: use analogous (by comparison), parametric (rates × quantities), three‑point (optimistic, most likely, pessimistic), bottom‑up (roll up from detailed tasks), and reserve analysis as appropriate.
- Consider drivers: resource availability and skill, productivity, learning curve, work windows, dependencies, constraints, tools, quality standards, and known risks.
- Calculate durations: apply chosen methods, convert to working time using calendars, and where using three‑point, compute an expected value and a range.
- Assess uncertainty: add time contingency for known risks in activities or as task buffers; keep any management reserve separate from the baseline.
- Document the basis: sources, assumptions, methods, ranges, confidence level, and key constraints for each estimate.
- Update records: revise activity attributes, risk and assumptions logs, lessons learned, and schedule data; share for review and agreement.
Quality & Acceptance Checklist
- Each activity has a duration in working time units and aligns with the defined scope.
- Assumptions and constraints affecting time are clearly documented.
- Estimation method used and data sources are recorded and traceable.
- Resource calendars, availability, and skill levels are reflected in the numbers.
- Uncertainty is expressed as ranges and/or confidence levels; risk‑based contingency is visible, not hidden.
- Dependencies, leads, and lags are explicit and justifiable.
- Estimates are reviewed by the people doing the work and relevant experts.
- Units are consistent across all activities and milestones.
- The basis of estimates is stored for future updates and audits.
- Updates are triggered when scope, resources, or risk responses change.
Common Mistakes & Exam Traps
- Confusing effort (person‑hours) with duration (elapsed time), especially when resource availability is part‑time.
- Ignoring calendars and resource constraints, leading to calendar‑day estimates instead of working‑day estimates.
- Using analogous estimates when projects are not truly comparable, or parametric rates without validated productivity data.
- Providing single‑point numbers with no ranges or risk consideration, or hiding padding instead of using transparent contingency.
- Estimating without involving those who will perform the work, increasing optimism bias.
- Failing to update durations after approved scope changes or risk responses like crashing or fast tracking.
- Assuming adding people will always shorten duration, ignoring coordination overhead and task type.
- Misusing leads and lags to mask schedule problems rather than modeling real dependencies.
PMP Example Question
A specialist needed for a critical activity will be available only 50% next month. The team previously estimated the activity as 40 hours of effort over one week. What should the project manager do to improve the duration estimate?
- Add a management reserve to the schedule to cover the risk.
- Apply the resource calendar and re‑estimate duration based on 50% availability.
- Add more people to the activity to keep the one‑week duration.
- Ask the sponsor to confirm the one‑week deadline.
Correct Answer: B — Apply the resource calendar and re‑estimate duration based on 50% availability.
Explanation: Duration depends on resource availability. With half‑time availability, 40 hours of effort will span about two weeks of elapsed time, assuming no other constraints.
HKSM