Resource requirements
Resource requirements is an analysis technique used to determine the types, quantities, skill levels, and timing of people, equipment, materials, and facilities needed to perform project work. It converts the WBS and schedule into time-phased demand to support planning, acquisition, and cost estimation.
Key Points
- Defines what resources are needed, in what quantities, with which skills, and when they are required.
- Derived from the WBS, activity attributes, and the current schedule or roadmap.
- Covers labor and non-labor resources, including equipment, materials, facilities, and services.
- Creates time-phased demand that supports budgeting, staffing, procurement, and resource leveling.
- Includes explicit assumptions, calendars, productivity rates, and constraints.
- Iterative and progressively elaborated as scope, estimates, and availability change.
Purpose of Analysis
The purpose is to ensure the project has the right resources in the right quantities at the right times to execute planned work. It enables realistic schedules and budgets, guides acquisition and procurement decisions, highlights bottlenecks, and informs trade-offs such as make-or-buy or sequencing changes.
Method Steps
- Review scope and WBS to understand deliverables and work packages.
- List activities and activity attributes, including duration assumptions and dependencies.
- Identify resource types per activity: roles, skills, equipment, materials, facilities, and services.
- Estimate quantities and skill levels needed per activity, using historical data and productivity rates.
- Determine timing and usage profiles (full-time, part-time, effort per day, quantity per period).
- Apply calendars, shifts, and availability constraints for teams, equipment, and facilities.
- Aggregate activity-level needs into a time-phased view (e.g., weekly resource histogram).
- Compare demand to known supply; note gaps, peaks, and conflicts.
- Document assumptions, risks, and alternatives (e.g., acquire vs rent, different skills, sequencing).
- Review with stakeholders and update the resource plan, estimates, and schedule as needed.
Inputs Needed
- Scope baseline and WBS with work package details.
- Activity list, activity attributes, and preliminary schedule or roadmap.
- Resource breakdown structure, role definitions, and skill matrices.
- Organizational and resource calendars, shifts, and location constraints.
- Historical data, productivity rates, and benchmarks.
- Cost rates for labor, equipment, and materials.
- Risk register, assumptions log, and known constraints.
- Procurement strategy, supplier lead times, and contract terms if applicable.
Outputs Produced
- Activity-level resource requirements (types, quantities, skill levels, timing).
- Time-phased resource demand (e.g., histograms or heat maps).
- Lists of long-lead and critical-skill resources.
- Updates to the resource plan, RAM/RACI, and resource calendars.
- Inputs to cost estimates and budget based on resource rates and usage.
- Assumptions, risks, and basis-of-estimate documentation.
- Recommended options for addressing gaps (leveling, resequencing, outsourcing).
Interpretation Tips
- Focus on periods with demand spikes; these often drive schedule risk.
- Check critical-path activities for scarce skills or single points of failure.
- Validate that demand aligns with calendars, holidays, and maintenance windows.
- Assess feasibility against actual supply; propose alternatives where gaps exist.
- Translate demand into cost using rate cards to confirm budget realism.
- Revisit requirements after major scope or schedule changes and after learning from actuals.
Example
A project identifies 120 person-days of specialized testing over 6 weeks, two test environments, and 40 units of consumables. Aggregating by week shows a peak need of 5 testers in week 3, but only 3 are available. Options considered include shifting two activities, contracting 2 testers for weeks 2-4, or extending the schedule by one week. The analysis informs the cost impact and the recommended option.
Pitfalls
- Listing only roles without quantities, timing, or skill levels.
- Ignoring non-labor needs such as environments, tools, and materials.
- Using single-point estimates without ranges or productivity assumptions.
- Not accounting for calendars, learning curves, or ramp-up time.
- Failing to aggregate and compare demand to actual availability.
- Omitting long-lead items and supplier lead times.
- Weak stakeholder review, leading to late surprises and rework.
PMP Example Question
A project schedule is approved, but the team suspects a mid-project bottleneck due to a scarce specialist role. What should the project manager do next to address this risk?
- Create a RACI matrix to clarify responsibilities.
- Perform resource requirements analysis to quantify time-phased demand for the specialist and compare it to availability.
- Submit a change request to increase the budget for staffing.
- Decide to outsource the specialist work immediately.
Correct Answer: B — Perform resource requirements analysis to quantify time-phased demand for the specialist and compare it to availability.
Explanation: You need data on when and how much of the specialist is required before choosing solutions such as leveling, resequencing, or outsourcing. The analysis informs, rather than assumes, the corrective action.
HKSM