Acquire Resources

Resources/Executing/Acquire Resources
Inputs Tools & Techniques Outputs

Inputs, tools & techniques, and outputs for this process.

Securing the people, equipment, materials, facilities, and services the project needs, and confirming their availability and commitments at the right time and cost.

Purpose & When to Use

  • Turn planned resource needs into real assignments, contracts, and access so work can start on time.
  • Balance skills, capacity, cost, location, and policies to select the best-fit resources.
  • Covers internal staff, external vendors, and physical assets like tools, equipment, and facilities.
  • Used before each phase or activity that requires resources, and any time replacements or additional resources are needed.

Mini Flow (How It’s Done)

  • Review the resource plan, schedule, budget, and sourcing approach to confirm what is needed and when.
  • Check internal pools and calendars for available people and assets; identify gaps and constraints.
  • Define selection criteria such as skills, experience, cost, availability, time zone, and performance history.
  • Decide internal versus external sourcing; negotiate with functional managers or engage procurement as appropriate.
  • Assess candidates or suppliers using a transparent decision method; document rationale.
  • Secure formal commitments such as assignment approvals, purchase orders, or contracts.
  • Prepare onboarding and logistics, including access, tools, licenses, workspace, and initial training.
  • If demand exceeds supply, propose trade-offs such as schedule changes, scope adjustments, or phased staffing.
  • Update resource calendars, the schedule, cost forecasts, risks, and assumptions; communicate assignments and start dates.

Quality & Acceptance Checklist

  • Roles and responsibilities are clear, with required skills and capacity specified.
  • Selected resources meet skill, experience, and quality expectations, verified by evidence.
  • Availability aligns with planned dates and time commitments; time zone impacts are addressed.
  • Costs fit the budget; rates and fees are agreed and approved.
  • Formal agreements are in place, such as statements of work, purchase orders, or NDAs.
  • Onboarding is complete, including system access, tools, workspace, and compliance training.
  • Resource calendars, schedule activities, and cost forecasts are updated and communicated.
  • Backups or cross-coverage are identified for critical roles and single points of failure.
  • Communication channels and escalation paths are defined for internal and vendor resources.
  • Key assumptions and constraints are recorded and understood by stakeholders.

Common Mistakes & Exam Traps

  • Mixing up acquiring resources with developing the team or managing team performance.
  • Focusing only on people and forgetting equipment, facilities, materials, and services.
  • Assuming the project manager can hire directly when negotiation with functional managers or procurement is required.
  • Choosing the cheapest option without applying predefined selection criteria and availability checks.
  • Starting work before formal commitments, access, and safety or compliance requirements are met.
  • Failing to update the schedule, budget, and risk register after resource decisions.
  • Ignoring virtual team needs such as time zones, collaboration tools, and communication norms.
  • Escalating to the sponsor too early instead of first negotiating or exploring internal options.

PMP Example Question

A critical activity starts next week, but the assigned specialist is now unavailable due to another department’s priority. What should the project manager do first?

  1. Update the schedule to show a delay and notify stakeholders.
  2. Escalate to the sponsor to resolve the resource conflict.
  3. Negotiate with the functional manager to secure an available, equally qualified replacement.
  4. Submit a change request to reduce scope for the upcoming activity.

Correct Answer: C — Negotiate with the functional manager to secure an available, equally qualified replacement.

Explanation: In acquiring resources, the project manager first seeks internal solutions through negotiation to meet the need and maintain the plan. Baselines or escalations come after attempting viable options.

Project Management Bootcamp

Embark on a transformative journey with our Project Management Bootcamp at HK School of Management. Elevate from beginner to pro using the latest PMBOK and Process Groups Practice Guide. Our unique, engaging approach makes learning interactive and fun, replacing dull slides with dynamic doodles and real-life scenarios.

This hands-on program includes working on two full project plans. The first evolves as you learn, while the second culminates in a comprehensive plan, solidifying your expertise. You'll navigate real-world challenges, backed by quizzes and in-depth analysis, avoiding common pitfalls and setting you on a path to success.

Enhance your learning with downloadable materials and templates, invaluable for your future projects. The course covers essential topics like PMI, PMO, PMBOK, and project management ethics, delving into critical process groups and key areas such as scope, schedule, cost, and stakeholder management.

Learn from seasoned professionals and join a community of enthusiastic lifelong learners. Ready to master project management and lead with confidence? Enroll now and start your transformation!



Launch your Agile career!

HK School of Management helps you master Agile and Scrum—faster. Learn practical playbooks, AI-powered prompts, and real-world workflows to plan smarter, deliver sooner, and keep stakeholders aligned. For the price of lunch, you’ll get templates, tools, and step-by-step guidance to level up your projects. Backed by our 30-day money-back guarantee—zero risk, clear path to results.

Learn More