8.1 Close Project or Phase
| 8.1 Close Project or Phase | ||
|---|---|---|
| Inputs | Tools & Techniques | Outputs |
|
||
Purpose & When to Use
- Formally finish a project or phase by confirming deliverables are accepted and all work is complete.
- Transfer ownership of outputs to operations or the customer, and make sure support is in place.
- Close contracts, reconcile finances, archive records, and release people and resources.
- Capture lessons learned and publish a final performance report to inform future work.
- Use at the end of each phase, at overall project completion, or when work is terminated early.
Mini Flow (How It’s Done)
- Confirm scope completion: verify all requirements are met and outstanding work is documented.
- Obtain formal acceptance: secure written sign-off from the customer or sponsor on completed deliverables.
- Complete transition: hand over deliverables, training, support plans, and access to the receiving organization.
- Settle finances: ensure invoices are paid, accruals cleared, and the budget is reconciled.
- Close procurements: confirm all vendor obligations are met, receive completion certificates, and archive correspondence.
- Resolve open items: close or document disposition of issues, change requests, and risks, noting any residual risks.
- Update records: finalize baselines and logs, update benefits information, and record actual performance versus plan.
- Compile lessons learned: summarize what went well, what to improve, and recommended actions for future teams.
- Prepare and circulate the final report: include objectives, outcomes, variances, benefits status, and key insights.
- Release resources: formally release the team, recognize contributions, and update resource calendars.
- Archive and communicate closure: store all artifacts in the organization’s repository and notify stakeholders the project or phase is closed.
Quality & Acceptance Checklist
- All deliverables verified and accepted with documented sign-off.
- Requirements coverage confirmed; traceability shows complete or formally waived items.
- Quality criteria met; test results and any deviations approved.
- All change requests and issues are closed or have approved disposition.
- Risks are closed or have owners for any residual risks.
- Operational handover completed: manuals, training, licenses, access, and support contacts provided.
- Service or operations team acceptance obtained, including warranty or support arrangements.
- Contracts closed: final deliverables accepted, payments made, claims resolved, and closeout letters filed.
- Financials reconciled: budget versus actuals documented; assets and inventory accounted for.
- Final report shared; lessons learned recorded and stored in the knowledge repository.
- Team and stakeholder closure communications sent; resources released in HR and scheduling systems.
- All records archived per policy and retention rules.
Common Mistakes & Exam Traps
- Ending work without formal acceptance; always seek written sign-off before declaring closure.
- Forgetting procurement closure; vendor contracts must be formally closed, even if work is done.
- Skipping transition to operations; ensure support model, access, and training are in place.
- Leaving open issues or change requests; close or document their disposition and owners.
- Ignoring benefits information; update expected versus realized benefits and hand over to the benefits owner.
- Not archiving documents; store all key records for audits and future reuse.
- Thinking closure happens only at project end; it also applies at phase gates and early termination.
- Treating lessons learned as an afterthought; summarize and share insights as part of closure.
PMP Example Question
A project’s deliverables are complete and accepted. What should the project manager do next to close the project?
- Release the team and celebrate the achievement.
- Update the schedule and start the next project.
- Complete financial and contract closure, archive records, and issue the final report.
- Conduct a mid-project review to capture lessons learned.
Correct Answer: C — Complete financial and contract closure, archive records, and issue the final report.
Explanation: After acceptance, the manager finalizes administrative and procurement closure, archives documents, and publishes the final report before releasing resources.
HKSM