5.21 Perform Quantitative Risk Analysis

5.21 Perform Quantitative Risk Analysis
Inputs Tools & Techniques Outputs

A data-driven assessment that models how identified risks and general uncertainty could change project cost and schedule, producing probabilities, ranges, and guidance for reserves and responses.

Purpose & When to Use

  • Estimate the likelihood of meeting key dates and budgets using numbers, not just ratings.
  • Size cost and schedule contingency based on modeled uncertainty.
  • Identify which risks and assumptions drive the most variance.
  • Compare alternatives or response strategies using expected value and scenarios.
  • Use after qualitative risk prioritization, and on projects that are large, complex, or have tight targets or high uncertainty.
  • Repeat at major milestones or after significant scope, estimate, or risk changes.

Mini Flow (How It’s Done)

  • Confirm inputs and data quality: risk register with well-defined risks, schedule network, cost estimates, assumptions, and constraints.
  • Build the model: add uncertainty to durations and costs (e.g., three-point estimates) and include discrete risk events with probabilities and impacts.
  • Select distributions and dependencies: choose suitable probability distributions and model correlations where variables move together.
  • Run analysis: use simulation for cost and/or schedule, perform sensitivity checks (e.g., tornado charts), and use decision trees or expected value where choices exist.
  • Interpret results: review percentiles (e.g., P50, P80), ranges, probability of meeting targets, and the top risk drivers.
  • Decide and update: propose contingency reserves, refine risk responses, adjust targets if needed, and update the risk report and risk register.
  • Communicate and iterate: explain assumptions and confidence levels, then rerun when plans or risks change.

Quality & Acceptance Checklist

  • Scope, schedule, and cost models reflect the current baseline and logic ties are valid.
  • Key threats and opportunities are modeled, with clear probabilities and impacts.
  • Uncertainty ranges for major estimates are justified and sourced.
  • Chosen distributions and correlations are reasonable and documented.
  • Outputs include percentiles, probability of meeting key targets, and a list of main risk drivers.
  • Recommended contingency is traceable to analysis results, not arbitrary padding.
  • Assumptions, data quality limits, and scenario choices are recorded.
  • Stakeholders reviewed results and understand confidence levels and implications.

Common Mistakes & Exam Traps

  • Confusing qualitative with quantitative analysis; quantitative uses numeric models and probabilities, not just risk ratings.
  • Assuming it is required on every project; it is used when the benefit outweighs the effort and data is sufficient.
  • Ignoring opportunities; include positive impacts as well as threats in the model.
  • Leaving out correlations; dependencies between variables can materially change ranges.
  • Using point estimates only; always include uncertainty ranges for key costs and durations.
  • Misreading percentiles; P80 is not a guarantee, it is a confidence level under stated assumptions.
  • Double counting reserves; contingency comes from analysis for known-unknowns, while management reserve is separate for unknown-unknowns.
  • Running simulations on a weak schedule; missing logic ties or unrealistic calendars produce misleading results.

PMP Example Question

Your sponsor asks for the probability of finishing within the approved budget and a data-backed recommendation for cost contingency. You have already prioritized risks using likelihood and impact scores. What should you do next?

  1. Add a fixed percentage contingency based on organizational policy.
  2. Perform quantitative risk analysis using a cost model with uncertainties and discrete risks.
  3. Update the risk register with more qualitative categories.
  4. Request management reserve to cover unknown risks.

Correct Answer: B — Perform quantitative risk analysis using a cost model with uncertainties and discrete risks.

Explanation: The sponsor wants probabilities and defensible contingency. This requires quantitative analysis using a numerical model, not qualitative scoring or arbitrary percentages.

How To Land the Job and Interview for Project Managers Course

Take the next big step in your project management career with HK School of Management. Whether you're breaking into the field or aiming for your dream job, this course gives you the tools to stand out, impress in interviews, and secure the role you deserve.

This isn’t just another job-hunting guide—it’s a tailored roadmap for project managers. You’ll craft winning resumes, tackle tough interview questions, and plan your first 90 days with confidence. Our hands-on approach includes real-world examples, AI-powered resume hacks, and interactive exercises to sharpen your skills.

You'll navigate the hiring process like a pro, with expert insights on personal branding, salary negotiation, and career growth strategies. Plus, downloadable templates and step-by-step guidance ensure you're always prepared.

Learn from seasoned professionals and join a community of ambitious project managers. Ready to land your ideal job and thrive in your career? Enroll now and take control of your future!



Launch your career!

HK School of Management delivers top-tier training in Project Management, Job Search Strategies, and Career Growth. For the price of a lunch, you’ll gain expert insights into landing your dream PM role, mastering interviews, and negotiating like a pro. With a 30-day money-back guarantee, there’s zero risk—just a clear path to success!

Learn More