Monitor and Control Finances

Finance/Monitoring and Controlling/Monitor and Control Finances
Inputs Tools & Techniques Outputs

Inputs, tools & techniques, and outputs for this process.

Ongoing oversight of project spending and forecasts to compare against the approved cost baseline and funding limits, analyze variances, predict outcomes, and implement corrective actions to keep the project financially viable.

Purpose & When to Use

Monitor and Control Finances keeps the project affordable and aligned with approved funding. It links actual cost performance to the cost baseline, forecasts final cost, and triggers timely corrective or preventive actions. Use it throughout the project from the moment a budget baseline exists, with tighter cadence during heavy spend periods, when major risks materialize, or after scope or schedule changes. It applies to both adaptive and predictive approaches and supports value delivery by protecting financial outcomes.

Mini Flow (How It’s Done)

  • Confirm baselines and funding limits. Ensure the cost baseline is time-phased (S-curve), includes contingency reserve, and is distinct from management reserve and overall funding limits.
  • Collect actuals and commitments. Capture incurred costs, accruals, invoices, and approved purchase orders; reconcile with the work performed window.
  • Measure performance. Calculate EV, PV, AC, CPI, and SPI; review burn rate, unit costs, and cash flow trends; visualize with S-curves and control charts.
  • Forecast outcomes. Update ETC and EAC using appropriate methods (e.g., EAC = AC + remaining work at planned, current, or composite efficiency); compute TCPI against BAC or approved EAC.
  • Analyze variances and drivers. Identify quantity overruns, rate changes, productivity shifts, rework, scope growth, inflation, currency effects, and reserve usage.
  • Decide and implement actions. Adjust scope, sequence, or resourcing; negotiate with vendors; optimize make/buy; draw from contingency with justification; raise change requests if the baseline must change.
  • Update governance and records. Process change control for any baseline changes, refresh funding forecasts, update risk and assumption logs, and communicate impacts to stakeholders.
  • Control ongoing spend. Enforce spend thresholds, approvals, and audit trails; align payment terms, milestones, and sprint cadence with cash flow needs.

Quality & Acceptance Checklist

  • Actuals, commitments, and accruals are current, traceable to work performed, and reconciled with finance systems.
  • Cost baseline is time-phased, clearly separates contingency from management reserve, and reflects all approved changes.
  • EVM metrics (EV, PV, AC, CPI, SPI) are calculated correctly and interpreted consistently.
  • Forecasts (ETC, EAC) use suitable methods, key assumptions are stated, and sensitivity or scenario checks are performed.
  • TCPI is calculated and compared to realistic team and supplier performance capability.
  • Variance analysis identifies root causes and links to concrete corrective or preventive actions.
  • Reserve status is visible, drawdowns are justified, and remaining contingency is adequate for residual risk.
  • Cash flow remains within funding limits and timing; any funding gaps have mitigation plans.
  • Required financial reports are issued to stakeholders on the agreed cadence with clear, decision-ready insights.
  • All financial changes follow governance and are documented with an auditable trail.

Common Mistakes & Exam Traps

  • Treating sunk costs as a reason to continue work; decisions should be based on future value and remaining cost.
  • Confusing funding limit with cost baseline; exceeding a monthly or quarterly funding cap can be an issue even if BAC is unchanged.
  • Assuming management reserve is part of the cost baseline; it is controlled by governance and not performance-measured.
  • Using a single EAC formula for all cases; choose based on whether past cost performance will persist.
  • Ignoring accruals and committed costs, which hides true burn and causes late surprises.
  • Relying on percent complete without objective earned value or measurable progress criteria.
  • Misreading indices: CPI greater than 1.0 means cost efficiency (under budget); less than 1.0 means overrun.
  • Misapplying TCPI by comparing to BAC when EAC is already approved, or targeting an unachievable efficiency.
  • Failing to rebaseline after approved scope or major plan changes, leading to misleading variances.
  • Omitting risk response costs and inflation impacts from forecasts.

PMP Example Question

Midway through a project, CPI is 0.85 and SPI is 0.98. The team has identified rate increases and rework as main drivers. What should the project manager do next?

  1. Draw from management reserve to cover the overrun and continue work.
  2. Analyze root causes, update EAC and corrective actions, and submit a change request if the cost baseline must change.
  3. Rebaseline the schedule immediately to bring SPI back to 1.0.
  4. Ignore the cost variance because the schedule is nearly on track.

Correct Answer: B — Analyze root causes, update EAC and corrective actions, and submit a change request if the cost baseline must change.

Explanation: With sustained cost variance, update forecasts and implement corrective actions. If the baseline cannot be met, follow formal change control. Management reserve is not used without governance, and schedule rebaselining is unrelated to cost variance.

How To Land the Job and Interview for Project Managers Course

Take the next big step in your project management career with HK School of Management. Whether you're breaking into the field or aiming for your dream job, this course gives you the tools to stand out, impress in interviews, and secure the role you deserve.

This isn’t just another job-hunting guide—it’s a tailored roadmap for project managers. You’ll craft winning resumes, tackle tough interview questions, and plan your first 90 days with confidence. Our hands-on approach includes real-world examples, AI-powered resume hacks, and interactive exercises to sharpen your skills.

You'll navigate the hiring process like a pro, with expert insights on personal branding, salary negotiation, and career growth strategies. Plus, downloadable templates and step-by-step guidance ensure you're always prepared.

Learn from seasoned professionals and join a community of ambitious project managers. Ready to land your ideal job and thrive in your career? Enroll now and take control of your future!



Launch your career!

HK School of Management delivers top-tier training in Project Management, Job Search Strategies, and Career Growth. For the price of a lunch, you’ll gain expert insights into landing your dream PM role, mastering interviews, and negotiating like a pro. With a 30-day money-back guarantee, there’s zero risk—just a clear path to success!

Learn More