To-complete performance index

A forward-looking cost efficiency metric that indicates the performance needed on the remaining work to meet a selected cost target (BAC or EAC). It helps determine achievability and guides corrective actions during cost control.

Key Points

  • Shows the required cost efficiency for the remaining work to hit a chosen cost target.
  • Two variants: TCPI(BAC) = (BAC - EV) / (BAC - AC), and TCPI(EAC) = (BAC - EV) / (EAC - AC).
  • Compare TCPI to current CPI: TCPI > 1.0 means tougher-than-planned efficiency is needed; TCPI < 1.0 means the target is more attainable.
  • Use at project, control account, or work package level to focus interventions where they matter.
  • Drives decisions on cost containment, reforecasting (EAC/ETC), and whether to rebaseline.

Purpose of Analysis

  • Assess if the current cost target is realistic given actual performance to date.
  • Quantify how aggressively the team must perform to recover or maintain cost objectives.
  • Support decisions on corrective actions, funding requests, and stakeholder expectations.

Method Steps

  • Select the cost target: original BAC or a revised EAC if management has set a new goal.
  • Gather up-to-date EV and AC at the desired reporting level and period.
  • Calculate TCPI using the appropriate formula for the chosen target.
  • Compare TCPI to the current CPI and team capability to judge achievability.
  • Identify actions: reduce scope, increase productivity, adjust resources, negotiate rates, or revise the forecast.
  • Recommend a path: keep BAC, adopt a new EAC, or rebaseline; document rationale.
  • Monitor TCPI and CPI trends each cycle and update forecasts and reports.

Inputs Needed

  • BAC (Budget at Completion) for the relevant scope.
  • EV (Earned Value) to date for the same scope and time frame.
  • AC (Actual Cost) to date aligned with EV.
  • EAC (Estimate at Completion) if assessing against a revised target.
  • Current CPI (EV/AC) for context and comparison.
  • Approved changes, risk responses, and rate assumptions that affect remaining work.

Outputs Produced

  • Computed TCPI value against BAC and/or EAC.
  • Assessment of achievability versus current CPI and organizational constraints.
  • Recommended corrective or preventive actions and cost control measures.
  • Updated EAC/ETC and cost forecasts as needed.
  • Inputs to stakeholder reports, variance explanations, and management decisions.

Interpretation Tips

  • If TCPI(BAC) is much higher than CPI, meeting BAC is unlikely without significant changes.
  • If TCPI(EAC) is close to current CPI, the revised EAC is consistent with observed performance.
  • Values near 1.0 imply performance must match plan; higher than 1.1 indicates aggressive recovery is required.
  • If AC is at or above the target (BAC or EAC), the denominator approaches zero or turns negative, signaling the target is no longer attainable.
  • Use the same data cut and scope for EV and AC to avoid distorted ratios.

Example

Given BAC = 1,200,000; EV = 500,000; AC = 600,000.

  • TCPI(BAC) = (1,200,000 - 500,000) / (1,200,000 - 600,000) = 700,000 / 600,000 = 1.17.
  • Current CPI = EV / AC = 500,000 / 600,000 = 0.83.
  • Since 1.17 is far above 0.83, holding BAC is unlikely; consider revising EAC and implementing cost controls.
  • If a new EAC = 1,440,000 is adopted, TCPI(EAC) = (1,200,000 - 500,000) / (1,440,000 - 600,000) = 700,000 / 840,000 = 0.83, which aligns with current performance.

Pitfalls

  • Mixing BAC and EAC in the numerator or denominator and getting the wrong ratio.
  • Using stale EV/AC data or mismatched scope definitions between EV and AC.
  • Interpreting TCPI in isolation without comparing to CPI, resource capacity, and constraints.
  • Assuming TCPI > 1.0 is always achievable without considering schedule pressure and risk exposure.
  • Ignoring that a near-zero or negative denominator indicates the target is already unattainable.

PMP Example Question

A project has BAC = 1,200,000, EV = 600,000, and AC = 750,000. Management wants to meet the original BAC. What is the TCPI to achieve BAC?

  1. 0.80.
  2. 1.33.
  3. 0.75.
  4. 1.20.

Correct Answer: B — 1.33.

Explanation: TCPI(BAC) = (BAC - EV) / (BAC - AC) = (1,200,000 - 600,000) / (1,200,000 - 750,000) = 600,000 / 450,000 = 1.33. Values above 1.0 indicate the team must outperform the original plan on remaining work.

Project Management Bootcamp

Embark on a transformative journey with our Project Management Bootcamp at HK School of Management. Elevate from beginner to pro using the latest PMBOK and Process Groups Practice Guide. Our unique, engaging approach makes learning interactive and fun, replacing dull slides with dynamic doodles and real-life scenarios.

This hands-on program includes working on two full project plans. The first evolves as you learn, while the second culminates in a comprehensive plan, solidifying your expertise. You'll navigate real-world challenges, backed by quizzes and in-depth analysis, avoiding common pitfalls and setting you on a path to success.

Enhance your learning with downloadable materials and templates, invaluable for your future projects. The course covers essential topics like PMI, PMO, PMBOK, and project management ethics, delving into critical process groups and key areas such as scope, schedule, cost, and stakeholder management.

Learn from seasoned professionals and join a community of enthusiastic lifelong learners. Ready to master project management and lead with confidence? Enroll now and start your transformation!



Launch your career!

HK School of Management provides world-class training in Project Management, Lean Six Sigma, and Agile Methodologies. Just for the price of a lunch you can transform your career, and reach new heights. With 30 days money-back guarantee, there is no risk.

Learn More