Assess and Implement Changes
| Governance/Monitoring and Controlling/Assess and Implement Changes | ||
|---|---|---|
| Inputs | Tools & Techniques | Outputs |
|
||
Inputs, tools & techniques, and outputs for this process.
A structured practice to evaluate requested changes, decide with the right authority, and implement approved changes in a controlled way by updating plans, baselines, product components, and records.
Purpose & When to Use
- Provide a consistent, transparent way to evaluate proposed changes and decide whether to proceed.
- Protect scope, schedule, cost, quality, and product integrity while enabling improvements and compliance.
- Use whenever a request may affect baselines, value, risks, resources, contracts, or regulatory obligations.
- Apply in all delivery approaches: predictive uses formal control boards, hybrid uses tiered authority, and adaptive uses backlog refinement and timeboxed planning.
- Use fast-track paths for urgent or safety-critical changes, followed by post-implementation review and documentation.
Mini Flow (How It’s Done)
- Capture the request: describe the need, benefits, urgency, and acceptance criteria; assign an owner; log it in the change log or backlog.
- Triage the type: defect repair, corrective action, preventive action, or enhancement; confirm required supporting information.
- Analyze impacts: assess scope, schedule, cost, quality, value, risks, resources, dependencies, technical feasibility, and compliance; outline options with estimates.
- Engage stakeholders: consult the team, product owner or sponsor, SMEs, vendors, and affected users to validate assumptions and constraints.
- Decide with the right authority: product owner, sponsor, project manager within limits, or change control board; document approve, defer, or reject with rationale.
- Plan implementation: define tasks, owner, timing, testing, acceptance, communications, training, and rollback; update the backlog or work plan.
- Update baselines and documents: revise scope, schedule, and cost baselines as needed; update configuration items, requirements, risks, and contracts.
- Communicate the decision: inform stakeholders, synchronize with vendors, and set expectations on delivery and impacts.
- Implement and validate: execute the change, perform testing and integration, verify acceptance criteria, and release as planned.
- Close and learn: update the change log, configuration records, lessons learned, and performance metrics; monitor realized benefits and residual risks.
- Adaptive note: the product owner reorders the backlog; the team estimates and schedules the item into an upcoming iteration unless it is a critical fix that meets defined entry rules.
Quality & Acceptance Checklist
- The change request is clearly stated with business reason, expected value, and acceptance criteria.
- Impact analysis covers scope, schedule, cost, quality, value, risks, resources, dependencies, and compliance.
- Alternatives, including do-nothing and minimal viable change, are considered with rough estimates.
- Decision authority and approval path are correct for the change size and risk.
- Decision and rationale are recorded in the change log or backlog tool.
- Baselines and relevant documents are updated when required and version-controlled.
- Implementation plan includes owner, timeline, testing, integration, communication, training, and rollback.
- Stakeholders are informed of impacts and timing; vendor or contract updates are addressed.
- Risks and issues are updated, including triggers and contingency plans.
- Post-implementation validation confirms acceptance criteria and no unintended side effects.
- Lessons learned and configuration records are updated for traceability.
Common Mistakes & Exam Traps
- Implementing changes without proper approval or outside delegated limits.
- Skipping impact analysis before seeking a decision or escalating prematurely.
- Updating the schedule but not cost, scope, risks, or contracts, leading to misalignment.
- Assuming every change needs a formal board in agile settings; backlog prioritization by the product owner is a valid control mechanism.
- Changing in-flight iteration scope without defined urgent-change rules and team agreement.
- Confusing change control with configuration control; both are needed to manage versions and traceability.
- Ignoring non-functional requirements, regulatory impacts, or data and security implications.
- Lack of rollback or recovery plan for higher-risk changes.
- Not documenting emergency changes and skipping post-implementation review.
- Equating defect fixes with scope changes; repairs may still require analysis and coordination.
PMP Example Question
A stakeholder submits a change that improves compliance but may extend delivery by two weeks. What should the project manager do first?
- Implement the change immediately to avoid compliance risk.
- Log the request and work with the team to assess impacts before seeking approval.
- Send the request directly to the sponsor for a decision without analysis.
- Reject the change because it threatens the schedule baseline.
Correct Answer: B — Log the request and work with the team to assess impacts before seeking approval.
Explanation: The proper first step is to document and analyze impacts, then route to the appropriate decision authority. Implementing or rejecting without analysis bypasses change control.
HKSM