Project Value Estimation

Project Value Estimation is an SBOK tool for quantifying expected business value by weighing benefits, costs, risks, and timing of a Scrum project or major backlog items. It supports business justification, value-based prioritization, and go/hold/stop decisions at initiation and throughout delivery.

Key Points

  • Used to translate vision and benefits into measurable value metrics and scores.
  • Combines monetary models (ROI, NPV, payback) with relative techniques (value points, scoring grids).
  • Led by the Product Owner with stakeholder input; the Scrum Master facilitates the session.
  • Applied at initiation and refined continuously using Sprint Review feedback and actual velocity.
  • Produces risk-adjusted value ranges and prioritization inputs for the product backlog.
  • Directly informs go/hold/terminate decisions to maintain strong business justification.

Purpose of Analysis

The purpose is to determine whether the project and its epics are worth pursuing and in what order to deliver them. It brings transparency to expected outcomes, aligns stakeholders on trade-offs, and sets a baseline for tracking realized value over time.

Method Steps

  1. Clarify the product vision, target outcomes, and decision criteria with stakeholders.
  2. Define value criteria (e.g., revenue impact, cost savings, risk reduction, compliance, customer satisfaction).
  3. Gather inputs: benefit hypotheses, cost ranges, risk probabilities, timing, and dependencies.
  4. Select estimation models: ROI, NPV, payback period, value points, and a simple risk adjustment approach.
  5. Estimate benefits and costs using ranges; note key assumptions and uncertainties.
  6. Calculate metrics and risk-adjust the results; run sensitivity checks for best/likely/worst cases.
  7. Compare alternatives and prioritize epics/features based on value relative to effort and risk.
  8. Record assumptions, rationale, and decisions in the business justification and decision log.
  9. Revisit estimates each Sprint using empirical data from reviews, usage analytics, and velocity.

Inputs Needed

  • Product Vision Statement and high-level scope or epics.
  • Business case elements: market opportunity, target users, expected benefits.
  • Preliminary cost estimates, capacity or velocity forecasts, and constraints.
  • Risk register or risk list with probabilities and impacts.
  • Historic data, benchmarks, customer research, and stakeholder priorities.
  • Dependencies, compliance needs, and time-to-market considerations.

Outputs Produced

  • Value scorecards for epics/features (e.g., ROI/NPV/payback/value points with ranges).
  • Risk-adjusted value matrix and assumptions log.
  • Prioritization guidance for the product backlog and release goals.
  • Updated business justification and a continue/pivot/stop recommendation.
  • Baseline for tracking realized value across sprints and releases.

Interpretation Tips

  • Treat estimates as ranges, not precise predictions; communicate uncertainty explicitly.
  • Compare items on value relative to effort and risk, not absolute value alone.
  • Prefer simple, transparent models the team and stakeholders understand.
  • Re-estimate frequently; replace assumptions with real metrics from Sprint Reviews.
  • Consider intangible or strategic value (brand, compliance, learning) alongside financials.
  • Do not let sunk costs bias decisions; act on current value outlook.

Example

A Product Owner compares two epics for the first release. Epic A is expected to increase conversions and reduce churn; Epic B provides internal analytics.

Epic A: cost 3 sprints, value points 90, risk low-medium, payback estimated at 2 sprints. Epic B: cost 2 sprints, value points 45, risk low, payback estimated at 5 sprints.

After a simple risk adjustment and sensitivity check, Epic A maintains higher value per sprint. The team prioritizes Epic A first and documents assumptions to revisit after the first Sprint Review.

Pitfalls

  • Over-precision that hides uncertainty and false confidence.
  • Ignoring risk and time value of money when comparing options.
  • Equating low cost with high value without considering outcomes.
  • Anchoring on early estimates and failing to update with new data.
  • Omitting non-financial value such as compliance, safety, or learning.
  • Allowing stakeholder bias to outweigh transparent, agreed criteria.

PMP/SCRUM Example Question

During Create Project Vision, cost estimates increase and new risks surface for the top epic. What should the Scrum Master facilitate to support the Product Owner's next step?

  1. Lock the original estimates to prevent scope creep and continue as planned.
  2. Re-estimate project value using ranges and risk adjustments, then update backlog prioritization.
  3. Start with the most complex epic to reduce technical uncertainty regardless of value.
  4. Ask Developers to pick the easiest stories to show quick progress to stakeholders.

Correct Answer: B — Re-estimate project value using ranges and risk adjustments, then update backlog prioritization.

Explanation: When costs and risks change, value estimates must be refreshed and used to reprioritize. Scrum emphasizes maintaining business justification and value-based prioritization.

How To Land the Job and Interview for Project Managers Course

Take the next big step in your project management career with HK School of Management. Whether you're breaking into the field or aiming for your dream job, this course gives you the tools to stand out, impress in interviews, and secure the role you deserve.

This isn’t just another job-hunting guide—it’s a tailored roadmap for project managers. You’ll craft winning resumes, tackle tough interview questions, and plan your first 90 days with confidence. Our hands-on approach includes real-world examples, AI-powered resume hacks, and interactive exercises to sharpen your skills.

You'll navigate the hiring process like a pro, with expert insights on personal branding, salary negotiation, and career growth strategies. Plus, downloadable templates and step-by-step guidance ensure you're always prepared.

Learn from seasoned professionals and join a community of ambitious project managers. Ready to land your ideal job and thrive in your career? Enroll now and take control of your future!



Launch your career!

HK School of Management delivers top-tier training in Project Management, Job Search Strategies, and Career Growth. For the price of a lunch, you’ll gain expert insights into landing your dream PM role, mastering interviews, and negotiating like a pro. With a 30-day money-back guarantee, there’s zero risk—just a clear path to success!

Learn More