Total Float

The maximum time an activity can start later or take longer, relative to its early start, without pushing the overall project finish date or breaking any imposed schedule constraints.

Key Points

  • Indicates schedule flexibility that does not change the project's completion date or violate constraints.
  • Calculated as LS - ES or LF - EF in the network schedule.
  • Activities on the critical path typically have zero total float; negative float signals the plan cannot meet a required date.
  • Float on a path is shared by its activities; using it on one activity reduces what is available to others on the same path.

Example

Activity B has ES = day 5 and EF = day 9. Its LS = day 7 and LF = day 11. Total float = LS - ES = 2 days (or LF - EF = 2 days). B can start up to two days late or run two days longer without moving the project's finish or breaking a constraint.

PMP Example Question

A task shows a total float of 3 days. What does this allow the project manager to do?

  1. Delay the task by up to 3 days without affecting the project finish date.
  2. Delay the task by up to 3 days without affecting any successor's early start.
  3. Add 3 days of scope to the task without any impact.
  4. Crash the task by 3 days with no additional cost.

Correct Answer: A — Delay the task without moving the project completion date

Explanation: Total float is the time an activity can slip or extend relative to its early start without changing the project finish date or violating schedule constraints. Option B describes free float.

Project Management Bootcamp

Embark on a transformative journey with our Project Management Bootcamp at HK School of Management. Elevate from beginner to pro using the latest PMBOK and Process Groups Practice Guide. Our unique, engaging approach makes learning interactive and fun, replacing dull slides with dynamic doodles and real-life scenarios.

This hands-on program includes working on two full project plans. The first evolves as you learn, while the second culminates in a comprehensive plan, solidifying your expertise. You'll navigate real-world challenges, backed by quizzes and in-depth analysis, avoiding common pitfalls and setting you on a path to success.

Enhance your learning with downloadable materials and templates, invaluable for your future projects. The course covers essential topics like PMI, PMO, PMBOK, and project management ethics, delving into critical process groups and key areas such as scope, schedule, cost, and stakeholder management.

Learn from seasoned professionals and join a community of enthusiastic lifelong learners. Ready to master project management and lead with confidence? Enroll now and start your transformation!



Take Control of Project Performance!

HK School of Management helps you go beyond status reports and gut feelings. In this advanced course, you’ll master Earned Value Management (EVM) to objectively measure progress, forecast outcomes, and take corrective action with confidence. Learn how WBS quality drives performance, how control accounts really work, and how to use EAC, TCPI, and variance analysis to make smarter decisions—before projects drift off track. Built around real-world examples and hands-on exercises, this course gives you practical tools you can apply immediately. Backed by our 30-day money-back guarantee—low risk, high impact for serious project professionals.

Learn More