Total Float

The maximum time an activity can start later or take longer, relative to its early start, without pushing the overall project finish date or breaking any imposed schedule constraints.

Key Points

  • Indicates schedule flexibility that does not change the project's completion date or violate constraints.
  • Calculated as LS - ES or LF - EF in the network schedule.
  • Activities on the critical path typically have zero total float; negative float signals the plan cannot meet a required date.
  • Float on a path is shared by its activities; using it on one activity reduces what is available to others on the same path.

Example

Activity B has ES = day 5 and EF = day 9. Its LS = day 7 and LF = day 11. Total float = LS - ES = 2 days (or LF - EF = 2 days). B can start up to two days late or run two days longer without moving the project's finish or breaking a constraint.

PMP Example Question

A task shows a total float of 3 days. What does this allow the project manager to do?

  1. Delay the task by up to 3 days without affecting the project finish date.
  2. Delay the task by up to 3 days without affecting any successor's early start.
  3. Add 3 days of scope to the task without any impact.
  4. Crash the task by 3 days with no additional cost.

Correct Answer: A — Delay the task without moving the project completion date

Explanation: Total float is the time an activity can slip or extend relative to its early start without changing the project finish date or violating schedule constraints. Option B describes free float.

Leadership for Project Managers Course

Lead with clarity, confidence, and real impact. This Leadership for Project Managers course turns day-to-day challenges—unclear priorities, tough stakeholders, and cross-functional friction—into opportunities to guide teams and deliver outcomes that matter.

You’ll learn practical leadership skills tailored to project realities: setting direction without overcontrol, creating alignment across functions, and building commitment even when authority is limited. We go beyond theory with tools you can use immediately—one-sentence visioning, stakeholder influence maps, decision framing, and feedback scripts that actually land.

Expect hands-on frameworks, real-world examples, and guided practice to prepare for tough moments—executive readouts, resistance from stakeholders, and high-stakes negotiations. Downloadable templates and checklists keep everything actionable when the pace gets intense.

Ready to influence without waiting for a bigger title? Join a community of ambitious PMs, sharpen your edge, and deliver with purpose—project after project.



Launch your Agile career!

HK School of Management helps you master Agile and Scrum—faster. Learn practical playbooks, AI-powered prompts, and real-world workflows to plan smarter, deliver sooner, and keep stakeholders aligned. For the price of lunch, you’ll get templates, tools, and step-by-step guidance to level up your projects. Backed by our 30-day money-back guarantee—zero risk, clear path to results.

Learn More