Start Date

A time marker tied to when a scheduled activity begins, commonly identified with a qualifier such as actual, planned, estimated, scheduled, early, late, target, baseline, or current.

Key Points

  • Start dates are labeled with qualifiers like actual, planned, estimated, scheduled/current, early, late, target, or baseline.
  • Early and late start come from network analysis; baseline start is from the approved plan; scheduled/current reflects the latest working schedule; actual start is when work truly began.
  • Dependencies, leads/lags, calendars, constraints, and resource leveling all influence start dates.
  • Schedule variance can be assessed by comparing current or scheduled start against the baseline start.

Example

Activity "Install wiring" has a Baseline Start of 02 Aug. After resource leveling, the Scheduled (current) Start moves to 04 Aug, and the Actual Start occurs on 05 Aug. The variance from baseline is +3 days.

PMP Example Question

In a schedule report, which start date qualifier indicates the date the activity truly began?

  1. Actual start
  2. Planned start
  3. Early start
  4. Late start

Correct Answer: A — Actual start date

Explanation: The actual start records the real-world date work began, while planned, early, and late are projections or limits from the plan and analysis.

ICS/OT Incident Response Plan: Write One That Works

Most OT incident response plans fail before anyone writes a word: no sponsor, no charter, no agreement on who decides. This workshop course takes you from a blank page to a plan your site approves and your operators can follow.

Each of the eight sections writes one chapter of your plan: the authority and scope, the inputs, severity in the language of the plant, command and decision rights, response steps, recovery and the readiness library.

You get the plan template, more than 40 templates and worksheets, 21 worked examples and a capstone with a full model answer.

50 videos, 7.7 hours. US$147 one-time through HKSM Courses. 30-day money-back guarantee when 50% or less consumed.

Explore the Course


ICS/OT Incident Response Plan course preview

Build the Sprint Reporting System, Not Another Prompt

AI Systems with Claude is our own course for Scrum Masters and Agile Project Managers, taught against one running project across eight teaching sections. You build five working systems and keep them: the sprint report machine, the retro intelligence system, the stakeholder comms engine, the backlog health monitor, and the risk and dependency tracker. Direct from HK School of Management and Technology, not on Udemy.

See What Is Included