Schedule Performance Index (SPI)

An indicator of schedule efficiency calculated by dividing earned value (EV) by planned value (PV).

Key Points

  • Formula: SPI = EV / PV; it compares authorized work accomplished to the work that was planned by this point.
  • Interpretation: SPI > 1.0 means ahead of schedule, SPI = 1.0 means on schedule, SPI < 1.0 means behind schedule.
  • Use only when PV > 0 and when EV and PV are measured against the same baseline; track SPI trends to monitor schedule health and forecast performance.
  • SPI shows relative schedule progress, not calendar time impact; combine with critical path analysis and CPI for a fuller picture.

Example

By the end of month 3, PV is 150 units of work and EV is 120 units. SPI = 120 / 150 = 0.80. The team is progressing at 80 percent of the planned rate, indicating the project is behind schedule.

PMP Example Question

A project reports EV = 275 and PV = 250 near the end of a phase. What is the SPI and how should the project manager interpret it?

  1. 0.91; the project is behind schedule
  2. 1.10; the project is ahead of schedule
  3. 1.00; the project is on schedule
  4. 1.10; the project is over budget

Correct Answer: B — SPI of 1.10; the project is ahead of schedule

Explanation: SPI = EV / PV = 275 / 250 = 1.10. An SPI greater than 1 indicates the project is ahead of schedule; cost status is not assessed by SPI.

Advanced Lean Six Sigma — Data-Driven Excellence

Solve complex problems, reduce variation, and improve performance with confidence. This course is designed for professionals who already know the basics and want to apply advanced Lean Six Sigma tools to real business challenges.

This is not abstract statistics or theory-heavy training. You’ll use Excel to perform real analysis, interpret results correctly, and apply tools like DMAIC, SIPOC, MSA, hypothesis testing, and regression without memorizing formulas or relying on expensive software.

You’ll learn how to measure baseline performance, analyze process capability, use control charts to maintain stability, and validate improvements using statistical evidence. Templates, worked examples, and structured walkthroughs help you apply each concept immediately.

Learn through a complete, real-world Lean Six Sigma project and develop the skills to lead data-driven improvements with credibility. If you’re ready to move beyond basics and make decisions backed by data, enroll now and take your Lean Six Sigma expertise to the next level.



Advance your Lean Six Sigma expertise!

HK School of Management helps you take Lean Six Sigma to the next level—without the overwhelm. Master advanced statistical tools, Excel-based analysis, and real-world improvement techniques to solve complex problems with confidence. For the price of lunch, you get practical templates, guided examples, and hands-on project experience you can use immediately at work. Backed by our 30-day money-back guarantee—zero risk, real impact.

Learn More