planned value (PV)

The portion of the approved project budget allocated to the work planned to be finished by a specific point in time. Related measures include actual cost (AC), budget at completion (BAC), earned value (EV), estimate at completion (EAC), and estimate to complete (ETC).

Key Points

  • PV is the time-phased budget for the work scheduled to be completed by the status date.
  • At project completion, the total PV equals the BAC.
  • PV is used with EV and AC to compute SV (EV - PV) and SPI (EV / PV) in earned value analysis.
  • PV is derived from the cost baseline aligned to the schedule and excludes management reserve.

Example

A project has a BAC of $250,000. By the end of week 4, the plan targets 30% completion. PV = 0.30 x 250,000 = $75,000. If EV is $60,000 and AC is $80,000, then SV = EV - PV = -$15,000 and SPI = EV / PV = 0.80, indicating the project is behind schedule.

PMP Example Question

By the end of month 2, the plan calls for completing work worth $200,000 on a project with a BAC of $500,000. Actual cost to date is $230,000 and earned value is $180,000. What is the planned value (PV) at the end of month 2?

  1. $180,000
  2. $200,000
  3. $230,000
  4. $500,000

Correct Answer: B — the budgeted cost of the work planned by the status date

Explanation: PV is the portion of the approved budget scheduled to be completed by the status date: $200,000. EV ($180,000) is the value of work actually performed; AC ($230,000) is what was spent; BAC ($500,000) is the total authorized budget.

Leadership for Project Managers Course

Lead with clarity, confidence, and real impact. This Leadership for Project Managers course turns day-to-day challenges—unclear priorities, tough stakeholders, and cross-functional friction—into opportunities to guide teams and deliver outcomes that matter.

You’ll learn practical leadership skills tailored to project realities: setting direction without overcontrol, creating alignment across functions, and building commitment even when authority is limited. We go beyond theory with tools you can use immediately—one-sentence visioning, stakeholder influence maps, decision framing, and feedback scripts that actually land.

Expect hands-on frameworks, real-world examples, and guided practice to prepare for tough moments—executive readouts, resistance from stakeholders, and high-stakes negotiations. Downloadable templates and checklists keep everything actionable when the pace gets intense.

Ready to influence without waiting for a bigger title? Join a community of ambitious PMs, sharpen your edge, and deliver with purpose—project after project.



Advance your Lean Six Sigma expertise!

HK School of Management helps you take Lean Six Sigma to the next level—without the overwhelm. Master advanced statistical tools, Excel-based analysis, and real-world improvement techniques to solve complex problems with confidence. For the price of lunch, you get practical templates, guided examples, and hands-on project experience you can use immediately at work. Backed by our 30-day money-back guarantee—zero risk, real impact.

Learn More