planned value (PV)

The portion of the approved project budget allocated to the work planned to be finished by a specific point in time. Related measures include actual cost (AC), budget at completion (BAC), earned value (EV), estimate at completion (EAC), and estimate to complete (ETC).

Key Points

  • PV is the time-phased budget for the work scheduled to be completed by the status date.
  • At project completion, the total PV equals the BAC.
  • PV is used with EV and AC to compute SV (EV - PV) and SPI (EV / PV) in earned value analysis.
  • PV is derived from the cost baseline aligned to the schedule and excludes management reserve.

Example

A project has a BAC of $250,000. By the end of week 4, the plan targets 30% completion. PV = 0.30 x 250,000 = $75,000. If EV is $60,000 and AC is $80,000, then SV = EV - PV = -$15,000 and SPI = EV / PV = 0.80, indicating the project is behind schedule.

PMP Example Question

By the end of month 2, the plan calls for completing work worth $200,000 on a project with a BAC of $500,000. Actual cost to date is $230,000 and earned value is $180,000. What is the planned value (PV) at the end of month 2?

  1. $180,000
  2. $200,000
  3. $230,000
  4. $500,000

Correct Answer: B — the budgeted cost of the work planned by the status date

Explanation: PV is the portion of the approved budget scheduled to be completed by the status date: $200,000. EV ($180,000) is the value of work actually performed; AC ($230,000) is what was spent; BAC ($500,000) is the total authorized budget.

Advanced Lean Six Sigma — Data-Driven Excellence

Solve complex problems, reduce variation, and improve performance with confidence. This course is designed for professionals who already know the basics and want to apply advanced Lean Six Sigma tools to real business challenges.

This is not abstract statistics or theory-heavy training. You’ll use Excel to perform real analysis, interpret results correctly, and apply tools like DMAIC, SIPOC, MSA, hypothesis testing, and regression without memorizing formulas or relying on expensive software.

You’ll learn how to measure baseline performance, analyze process capability, use control charts to maintain stability, and validate improvements using statistical evidence. Templates, worked examples, and structured walkthroughs help you apply each concept immediately.

Learn through a complete, real-world Lean Six Sigma project and develop the skills to lead data-driven improvements with credibility. If you’re ready to move beyond basics and make decisions backed by data, enroll now and take your Lean Six Sigma expertise to the next level.



Lead with clarity, influence, and outcomes.

HK School of Management brings you a practical, no-fluff Leadership for Project Managers course—built for real projects, tight deadlines, and cross-functional teams. Learn to set direction, align stakeholders, and drive commitment without relying on title. For the price of a lunch, get proven playbooks, and downloadable templates. Backed by a 30-day money-back guarantee—zero risk, high impact.

Learn More