Lag

A planned waiting period that delays the start or finish of a successor activity relative to its predecessor in a dependency link.

Key Points

  • Lag is a delay applied to the relationship between activities (FS, SS, FF, SF), not to the activities themselves.
  • It is usually a positive duration that postpones the successor; a negative value would represent a lead (accelerating the successor).
  • It models non-work waiting time such as curing, drying, shipping, or approval wait periods.
  • Defined in the schedule network as a duration or time unit on the dependency link and does not consume resources.

Example

Activity A: Pour concrete. Activity B: Strip forms. The relationship is Finish-to-Start with a 2-day lag to allow the concrete to cure. B cannot start until 2 days after A finishes.

PMP Example Question

A schedule shows Activity B cannot start until three days after Activity A finishes, even though A is complete. What is this three-day period called?

  1. Lead
  2. Float
  3. Lag
  4. Management reserve

Correct Answer: C — a planned delay between a predecessor and its successor

Explanation: Lag is the intentional waiting time inserted on a dependency link; lead accelerates the successor, float is schedule flexibility, and reserves are contingency buffers.

Leadership for Project Managers Course

Lead with clarity, confidence, and real impact. This Leadership for Project Managers course turns day-to-day challenges—unclear priorities, tough stakeholders, and cross-functional friction—into opportunities to guide teams and deliver outcomes that matter.

You’ll learn practical leadership skills tailored to project realities: setting direction without overcontrol, creating alignment across functions, and building commitment even when authority is limited. We go beyond theory with tools you can use immediately—one-sentence visioning, stakeholder influence maps, decision framing, and feedback scripts that actually land.

Expect hands-on frameworks, real-world examples, and guided practice to prepare for tough moments—executive readouts, resistance from stakeholders, and high-stakes negotiations. Downloadable templates and checklists keep everything actionable when the pace gets intense.

Learn alongside professionals around the world working in project leadership and delivery.

Explore the Course


Take Control of Project Performance!

HK School of Management helps you go beyond status reports and gut feelings. In this advanced course, you will learn Earned Value Management (EVM) to measure progress, forecast outcomes, and take corrective action. Learn how WBS quality drives performance, how control accounts work, and how to use EAC, TCPI, and variance analysis. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Learn More