Estimate to Complete (ETC)

The forecasted amount of money needed to complete all unfinished work on the project.

Key Points

  • ETC represents only the future cost from today to project completion, not what has already been spent.
  • It links to total forecast: EAC = AC + ETC, so ETC = EAC - AC.
  • You can compute ETC by a bottom-up reestimate of remaining work or by deriving it from an EAC formula based on performance assumptions.
  • Official PMI wording: "The expected cost to finish all the remaining project work."

Example

A project has BAC = $500,000, EV = $250,000, and AC = $300,000. Assuming future cost performance will mirror past performance (use CPI), first find EAC: EAC = AC + (BAC - EV) / CPI. With CPI = EV / AC = 250,000 / 300,000 = 0.833, EAC ≈ 300,000 + 250,000 / 0.833 ≈ 300,000 + 300,000 = $600,000. Therefore, ETC = EAC - AC = 600,000 - 300,000 = $300,000.

PMP Example Question

A project reports AC = $1.2M, EV = $1.0M, and BAC = $2.0M. The PM expects future work to continue at the current CPI. What is the Estimate to Complete (ETC)?

  1. $0.8M
  2. $1.0M
  3. $1.2M
  4. $2.0M

Correct Answer: C — $1.2M

Explanation: CPI = EV/AC = 1.0/1.2 = 0.833. EAC = AC + (BAC - EV)/CPI = 1.2 + (1.0)/0.833 ≈ 2.4 (in millions). ETC = EAC - AC = 2.4 - 1.2 = 1.2M.

Advanced Project Management — Measuring Project Performance

Move beyond guesswork and status reporting. This course helps you measure real progress, spot problems early, and make confident decisions using proven project performance techniques. If you manage complex projects and want clearer visibility and control, this course is built for you.

This is not abstract theory. You’ll work step by step through Earned Value Management (EVM), learning how cost, schedule, and scope come together to show true performance. You’ll build a solid foundation in EVM concepts, understand why formulas work, and learn how performance data actually supports leadership decisions.

You’ll master Work Breakdown Structures (WBS), control accounts, and budget baselines, then apply core EVM metrics like EAC, TCPI, and variance analysis. Through a detailed real-world example, you’ll forecast outcomes, analyze trends, and understand contingencies and management reserves with confidence.

Learn how experienced project managers monitor performance, communicate results clearly, and take corrective action before projects slip. With practical exercises and hands-on analysis, you’ll be ready to apply EVM immediately. Enroll now and start managing performance with clarity and control.

Explore the Course


Run the drill before the incident runs you

Design, run and prove OT drills and tabletop exercises before an incident tests your team. OT Incident Drills and Exercises includes 24 lessons and practical exercise materials, delivered through HKSM Courses for US$47 one-time. 30-day money-back guarantee when 50% or less of the course has been consumed.

Explore the Course