Estimate to Complete (ETC)

The forecasted amount of money needed to complete all unfinished work on the project.

Key Points

  • ETC represents only the future cost from today to project completion, not what has already been spent.
  • It links to total forecast: EAC = AC + ETC, so ETC = EAC - AC.
  • You can compute ETC by a bottom-up reestimate of remaining work or by deriving it from an EAC formula based on performance assumptions.
  • Official PMI wording: "The expected cost to finish all the remaining project work."

Example

A project has BAC = $500,000, EV = $250,000, and AC = $300,000. Assuming future cost performance will mirror past performance (use CPI), first find EAC: EAC = AC + (BAC - EV) / CPI. With CPI = EV / AC = 250,000 / 300,000 = 0.833, EAC ≈ 300,000 + 250,000 / 0.833 ≈ 300,000 + 300,000 = $600,000. Therefore, ETC = EAC - AC = 600,000 - 300,000 = $300,000.

PMP Example Question

A project reports AC = $1.2M, EV = $1.0M, and BAC = $2.0M. The PM expects future work to continue at the current CPI. What is the Estimate to Complete (ETC)?

  1. $0.8M
  2. $1.0M
  3. $1.2M
  4. $2.0M

Correct Answer: C — $1.2M

Explanation: CPI = EV/AC = 1.0/1.2 = 0.833. EAC = AC + (BAC - EV)/CPI = 1.2 + (1.0)/0.833 ≈ 2.4 (in millions). ETC = EAC - AC = 2.4 - 1.2 = 1.2M.

AI Systems with Claude, for Scrum Masters and Project Managers

Most AI pilots in project management do not fail on the model. They fail because somebody pointed the thing at a decision instead of at a task. This course is built around that distinction, and around the work that follows once you get it right.

Eight teaching sections, taught against one running project from the first lecture to the last. You watch a system get built, then you build the same one against your own sprint. Nothing here is a demo that works only on the example.

You finish with five working systems and you keep them. The sprint report machine turns your board export and standup notes into the report you currently write by hand. The retro intelligence system tells you what the team keeps saying, not just what it said this time. The stakeholder comms engine drafts the update in the register the audience expects. The backlog health monitor flags the quiet decay nobody has time to check for. The risk and dependency tracker follows the chains that actually bite.

Seventy-six working files ship with it, across four sections, so every system is built against real sprint data rather than material invented for a slide. Four sprints of retrospectives, board exports, standup notes, backlog and risk data.

Explore the Course


Launch your career!

HK School of Management and Technology provides world-class training in Project Management with AI and Agile Methodologies. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Learn More