Earned Value (EV)

The budgeted value of the work actually completed to date, found by applying the authorized budget for that scope to the percent complete.

Key Points

  • EV represents how much value has been earned in budget terms for the work finished by the status date.
  • Basic formula: EV = Percent Complete × Budget for that scope (e.g., a work package budget or BAC for the whole project).
  • Used with AC (Actual Cost) and PV (Planned Value) to compute CV, SV, CPI, and SPI.
  • EV reflects progress against the baseline; it is not the money spent (AC) nor the amount planned by now (PV).

Example

A project has a BAC of USD 500,000. By the status date, the team has completed 40% of the total scope. EV = 0.40 × 500,000 = USD 200,000. If AC = USD 230,000 and PV = USD 250,000, then CV = EV − AC = −USD 30,000 (over budget) and SV = EV − PV = −USD 50,000 (behind schedule).

PMP Example Question

A work package has an authorized budget of USD 80,000 and is 35% complete at the status date. What is the Earned Value (EV)?

  1. USD 28,000
  2. USD 35,000
  3. USD 80,000
  4. USD 45,000

Correct Answer: A — EV is USD 28,000

Explanation: EV = Percent Complete × Budget = 0.35 × 80,000 = 28,000.

Project Management with AI: From Initiation to Closing

Build a practical project management process from initiation to closing with our Project Management: From Initiation to Closing with AI course. Learn how to move from informal project coordination to a structured, repeatable approach using PMBOK-aligned workflows, real examples, and professional templates.

This hands-on course follows a complete project lifecycle. You will learn how to write a project charter, define scope, build a work breakdown structure, develop a schedule, estimate costs, manage risks, engage stakeholders, execute the work, monitor performance, and close the project properly.

You will also learn how to use AI tools to accelerate project management work. The course includes reusable prompts, downloadable templates, assignments, and worked examples that show how project documents connect from one stage to the next.

The course is designed for professionals, team leads, coordinators, analysts, and new project managers who need practical skills they can apply at work. Enroll now and build the confidence to manage projects with structure, clarity, and control.

Explore the Course


Build complete project plans in minutes with AI

Learn how to use AI to create charters, WBSs, schedules, risk registers, and executive reports while staying in control. This course gives you prompt templates and practical workflows based on real project work. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Learn More