Earned Schedule (ES)

A time-based extension of Earned Value Management that assesses schedule performance in units of time rather than cost.

Key Points

  • ES translates the earned value (EV) into the point in time on the planned value curve where that EV would have been planned.
  • Core indicators: SV(t) = ES - AT (schedule variance in time) and SPI(t) = ES / AT (schedule performance index in time), where AT is the actual time elapsed to the status date.
  • Unlike traditional SPI and SV, ES-based metrics continue to show meaningful schedule performance near project completion.
  • Helps forecast finish dates, assess schedule buffers, and integrate time-focused insights with standard EVM cost metrics.

Example

A project is at week 20 (AT = 20). The earned value achieved to date equals the planned value that was scheduled for week 18. Therefore, ES = 18 weeks. SV(t) = 18 - 20 = -2 weeks (behind schedule), and SPI(t) = 18 / 20 = 0.90.

PMP Example Question

At the status date, AT = 24 weeks and ES = 21 weeks. What is the best interpretation of these results?

  1. The project is 3 weeks under budget.
  2. The project is 3 weeks ahead of schedule.
  3. The project is 3 weeks behind schedule based on time-focused EVM.
  4. The project is performing as planned because SPI is 1.0.

Correct Answer: C — Earned Schedule indicates the work accomplished corresponds to week 21 while 24 weeks have elapsed.

Explanation: SV(t) = ES - AT = 21 - 24 = -3 weeks, showing the project is 3 weeks behind schedule using the Earned Schedule method.

ICS/OT Incident Response Drills and Exercises

An incident response plan is only a theory until the people who must use it have run it under pressure. This course helps OT engineers, operations leaders, IT responders, and security teams turn a plan on paper into a tested capability.

Define safe states and manual fallback before an incident forces the decision. Build escalation paths, tabletop exercises, and scenarios that expose the gaps a document review cannot find.

Then turn the results into evidence: an after-action report, owned improvements, recovery checks, and a drill cadence that keeps the program alive after the exercise ends.

24 lessons, 2.4 hours. US$47 one-time through HKSM Courses. 30-day money-back guarantee when 50% or less consumed.

Explore the Course


ICS/OT Incident Response Drills and Exercises course preview

Stop Managing Admin. Start Leading the Future!

HK School of Management helps you learn AI prompt engineering for project work. Move beyond status reports and risk logs with practical prompt frameworks for everyday tasks. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Enroll Now