Early Start Date (ES)

In CPM scheduling, ES is the first moment the remaining portion of an activity is allowed to begin, determined by the schedule network relationships, the current data (status) date, and any imposed schedule constraints.

Key Points

  • Calculated during the forward pass of the critical path method.
  • Driven by network logic, the data/status date, and schedule constraints (e.g., SNET).
  • Determines Early Finish: EF = ES + activity duration.
  • On the critical path, ES equals LS because total float is zero.

Example

Activity B (3 days) has a finish-to-start relationship with Activity A. A completes at the end of day 5. The data date is day 5 and there are no constraints. The ES for B is day 6, so its EF is day 8.

PMP Example Question

Which statement best defines the Early Start Date (ES) of a schedule activity in CPM?

  1. The earliest time the remaining work can start, based on network logic, the data date, and any constraints.
  2. The latest time the activity can start without delaying the project finish.
  3. The actual start recorded for the activity.
  4. The planned start from the approved baseline.

Correct Answer: A — The earliest allowed start based on logic, status date, and constraints

Explanation: ES is computed in the forward pass using the schedule network logic, the current data/status date, and any schedule constraints to find the earliest feasible start.

Leadership for Project Managers Course

Lead with clarity, confidence, and real impact. This Leadership for Project Managers course turns day-to-day challenges—unclear priorities, tough stakeholders, and cross-functional friction—into opportunities to guide teams and deliver outcomes that matter.

You’ll learn practical leadership skills tailored to project realities: setting direction without overcontrol, creating alignment across functions, and building commitment even when authority is limited. We go beyond theory with tools you can use immediately—one-sentence visioning, stakeholder influence maps, decision framing, and feedback scripts that actually land.

Expect hands-on frameworks, real-world examples, and guided practice to prepare for tough moments—executive readouts, resistance from stakeholders, and high-stakes negotiations. Downloadable templates and checklists keep everything actionable when the pace gets intense.

Ready to influence without waiting for a bigger title? Join a community of ambitious PMs, sharpen your edge, and deliver with purpose—project after project.



Become an AI-First Agile Leader!

HK School of Management empowers you to master AI as your most powerful co-pilot—without the complexity. Transform your agile leadership with practical, prompt-based workflows and proven strategies designed for real-world scrum challenges. For the price of lunch, you get the tools to automate mundane tasks, refine backlogs with precision, and drive unprecedented efficiency in your team. Backed by our 30-day money-back guarantee—zero risk, real impact.

Learn More