Defect Repair

A deliberate action taken to change a product or component that does not meet requirements so that it becomes compliant.

Key Points

  • Addresses deliverables or components that fail to meet specifications or acceptance criteria.
  • Typically originates from inspections or testing and is submitted as a change request for approval.
  • Can impact scope, schedule, cost, and risk; plans and baselines may need updates.
  • Repaired items are re-tested or re-inspected to confirm they now comply.

Example

During quality inspection, several welded joints on a steel frame are found below strength requirements. The team submits a change request, receives approval, re-welds the affected joints, and then re-tests them to verify they meet the specification. This is defect repair.

PMP Example Question

While testing, 12 of 200 circuit boards fail tolerance limits. The project manager submits a change request to replace the faulty resistors on the affected units. What is this action?

  1. Corrective action to bring overall project performance back in line
  2. Preventive action to reduce the probability of future defects
  3. Defect repair to rework nonconforming outputs
  4. Workaround to handle an unplanned issue without formal approval

Correct Answer: C — Defect repair to rework nonconforming outputs

Explanation: The action changes defective deliverables to meet requirements, which is defect repair, not corrective or preventive action.

Leadership for Project Managers Course

Lead with clarity, confidence, and real impact. This Leadership for Project Managers course turns day-to-day challenges—unclear priorities, tough stakeholders, and cross-functional friction—into opportunities to guide teams and deliver outcomes that matter.

You’ll learn practical leadership skills tailored to project realities: setting direction without overcontrol, creating alignment across functions, and building commitment even when authority is limited. We go beyond theory with tools you can use immediately—one-sentence visioning, stakeholder influence maps, decision framing, and feedback scripts that actually land.

Expect hands-on frameworks, real-world examples, and guided practice to prepare for tough moments—executive readouts, resistance from stakeholders, and high-stakes negotiations. Downloadable templates and checklists keep everything actionable when the pace gets intense.

Learn alongside professionals around the world working in project leadership and delivery.

Explore the Course


Stop Managing Admin. Start Leading the Future!

HK School of Management helps you learn AI prompt engineering for project work. Move beyond status reports and risk logs with practical prompt frameworks for everyday tasks. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Enroll Now