cumulative flow diagram

A time-based chart that cumulatively displays how many features are done, how many are in each in-progress state, and how many remain in the backlog.

Key Points

  • Shows cumulative item counts per workflow state (Backlog, In Progress stages, Done) across time.
  • The vertical thickness between colored bands represents WIP; widening bands signal bottlenecks.
  • The slope of the Done band reflects throughput; steady, parallel bands suggest stable flow.
  • Supports forecasting completion, monitoring queues, and guiding WIP limit and process adjustments.

Example

A Kanban team tracks features weekly. Their cumulative flow diagram shows the Testing band growing faster than others while the Done band flattens. The team adds a tester and limits items entering Testing; over the next two weeks the Testing band narrows and the Done band steepens, restoring predictable flow.

PMP Example Question

Which artifact best visualizes completed features over time along with items in each intermediate state and in the backlog to identify bottlenecks?

  1. Sprint burndown chart
  2. Cumulative flow diagram
  3. Gantt chart
  4. Velocity chart

Correct Answer: B — cumulative flow diagram

Explanation: A cumulative flow diagram plots cumulative counts by state (Backlog, in-progress stages, Done) over time, revealing WIP, bottlenecks, and throughput. The other options do not show all states simultaneously.

AI-Prompt Engineering for Strategic Leaders

Stop managing administration and start leading the future. This course is built specifically for managers and project professionals who want to automate chaos and drive strategic value using the power of artificial intelligence.

We don't teach you how to program Python; we teach you how to program productivity. You will master the AI-First Mindset and the 'AI Assistant' model to hand off repetitive work like status reports and meeting minutes so you can focus on what humans do best: empathy, negotiation, and vision.

Learn the 5 Core Prompt Elements-Role, Goal, Context, Constraints, and Output-to get high-quality results every time. You will build chained sequences for complex tasks like auditing schedules or simulating risks, while navigating ethics and privacy with human-in-the-loop safeguards.

Move from being an administrative manager to a high-value strategic leader. Future-proof your career today with practical, management-focused AI workflows that map to your real-world challenges. Enroll now and master the language of the future.

Explore the Course


Advance your Lean Six Sigma expertise!

HK School of Management and Technology helps you take Lean Six Sigma to the next level without the overwhelm. Master advanced statistical tools, Excel-based analysis, and real-world improvement techniques to solve complex problems with confidence. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Learn More