Critical Path Activity
A task that lies on the project's critical path, meaning its timing directly sets the earliest possible project completion; any delay to it delays the overall finish date.
Key Points
- Part of the sequence that determines the project's minimum duration (the critical path).
- Typically has zero total float; a slip here pushes the project end date.
- Crashing or fast-tracking these tasks can shorten the overall schedule but may increase cost or risk.
- The set of critical activities can change as durations, resources, or dependencies change.
Example
In a construction project, the path A (3 days) - B (7 days) - C (10 days) totals 20 days, while a parallel path D (5 days) - E (8 days) totals 13 days. Activities A, B, and C are critical path activities. If B finishes 2 days late and nothing else changes, the project completion also moves 2 days later.
PMP Example Question
Which statement best describes a critical path activity?
- An activity with zero total float whose delay will delay the project completion date.
- An activity chosen because it is the most expensive work in the project.
- An activity that can slip without affecting any successor or the finish date.
- An activity that is not on the longest path but still uses the most resources.
Correct Answer: A — a task on the critical path (zero total float)
Explanation: Critical path activities govern the project's minimum duration; any delay to them directly delays the project's finish.