Bottom-Up Estimating

An estimating approach that calculates total project cost or duration by first estimating each detailed WBS work package and then summing those estimates to the higher levels.

Key Points

  • Starts at the lowest-level WBS components and rolls estimates up to summary levels.
  • Typically more accurate than top-down methods, but requires more time and effort.
  • Relies on a complete WBS and input from subject matter experts for each work package.
  • Creates traceable, documented estimates and a defensible basis of estimate.

Example

A project manager for an ERP rollout asks functional leads to estimate hours and costs for each WBS work package: data migration, interface development, testing, training, and deployment. After gathering these detailed estimates, the PM aggregates them to produce the overall project duration and budget.

PMP Example Question

Your team has finalized the WBS. You ask each work package owner to estimate effort and cost for their activities and then sum these values to determine the project totals. Which technique are you using?

  1. Bottom-up estimating
  2. Analogous estimating
  3. Parametric estimating
  4. Three-point estimating

Correct Answer: A — estimating by rolling up work package estimates

Explanation: Bottom-up estimating aggregates detailed WBS work package estimates. Analogous is top-down using historical data, parametric uses unit rates, and three-point applies uncertainty ranges to individual estimates.

ICS/OT Incident Drills and Tabletop Exercises

An incident response plan is only a theory until the people who must use it have run it under pressure. This course helps OT engineers, operations leaders, IT responders, and security teams turn a plan on paper into a tested capability.

Define safe states and manual fallback before an incident forces the decision. Build escalation paths, tabletop exercises, and scenarios that expose the gaps a document review cannot find.

Then turn the results into evidence: an after-action report, owned improvements, recovery checks, and a drill cadence that keeps the program alive after the exercise ends.

51 lessons, 4.8 hours of video, eight quizzes and four hands-on assignments. US$47 one-time through HKSM Courses. 30-day money-back guarantee when 50% or less consumed.

Explore the Course


ICS/OT Incident Drills and Tabletop Exercises course preview

Launch your career!

HK School of Management and Technology offers training in project management, job-search strategies, and career growth. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Learn More