Analogous Estimating
A method that estimates an activity's or a project's time or cost by drawing on data from comparable past work.
Key Points
- Top-down approach used when limited detail is available.
- Relies on historical results from similar projects and expert judgment.
- Requires adjustments for differences in size, complexity, scope, or location.
- Faster but typically less accurate than bottom-up or parametric estimating.
Example
A team delivered a data center upgrade last year in 8 months for USD 900,000. A new upgrade has a similar scope but slightly higher capacity. Using analogous estimating, the project manager uses last year's figures and applies a 10 percent uplift, forecasting about 8.8 months and USD 990,000 as a high-level estimate.
PMP Example Question
During project initiation, the sponsor requests a quick, high-level cost figure before detailed planning begins. Which estimating technique should the project manager use?
- Bottom-up estimating
- Analogous estimating
- Three-point estimating
- Parametric estimating
Correct Answer: B - Analogous estimating
Explanation: Analogous estimating provides a rapid, top-down estimate using data from similar past projects, making it suitable early in the project when detail is limited.