7.4 Control Scope

7.4 Control Scope
Inputs Tools & Techniques Outputs

Replace this with term.

Purpose & When to Use

Control Scope keeps the project focused on the agreed deliverables. It verifies what is completed against the scope baseline and manages any requested changes through a formal process. Use it throughout the project once the scope baseline is set, and apply it regularly in both predictive and adaptive life cycles.

Mini Flow (How It’s Done)

  • Review the scope baseline: scope statement, WBS, and WBS dictionary.
  • Collect actuals: completed work, deliverable status, and requirement fulfillment from the requirements traceability matrix.
  • Compare actuals to the baseline and analyze variances and trends.
  • Identify unapproved additions (scope creep) and stop them from proceeding.
  • Evaluate needed changes; submit formal change requests with impact analysis on schedule, cost, quality, risks, and benefits.
  • Process changes through integrated change control; implement only approved changes.
  • Update the scope baseline, WBS, RTM, and related plans and documents after approval.
  • Communicate status, variances, and decisions to stakeholders; adjust backlog or release plan in adaptive approaches.

Quality & Acceptance Checklist

  • Scope baseline is current, version-controlled, and accessible.
  • Each deliverable has clear, measurable acceptance criteria.
  • All scope changes are submitted, reviewed, and approved or rejected formally.
  • Requirements traceability matrix shows status, tests, and acceptance for each requirement.
  • Approved changes are reflected in the WBS, schedule, budget, and risks.
  • Variance analysis (e.g., scope performance, trend) is documented with actions.
  • Instances of gold plating or scope creep are recorded and corrected.
  • Stakeholder communications and acceptance records are complete and archived.

Common Mistakes & Exam Traps

  • Confusing Control Scope (monitor and manage changes) with Validate Scope (formal acceptance of completed deliverables).
  • Allowing team or stakeholders to add features without approval (gold plating or scope creep).
  • Updating schedule or cost without updating the scope baseline and WBS after a change is approved.
  • Skipping impact analysis before submitting or deciding on a change request.
  • Not using the requirements traceability matrix to verify each requirement’s status and tests.
  • Treating defect repair as a scope change without checking if it restores the baseline deliverable.
  • Assuming internal completion equals acceptance; acceptance must match stated criteria.

PMP Example Question

A stakeholder asks the team to add a minor feature. The team has started work on it to save time. What should the project manager do next?

  1. Allow the team to finish since the change is small and will delight the customer.
  2. Submit a formal change request and assess impacts before any additional work continues.
  3. Update the WBS and schedule to include the extra work and inform stakeholders.
  4. Reject the change immediately and forbid any future change requests.

Correct Answer: B — Submit a formal change request and assess impacts before any additional work continues.

Explanation: Only approved changes should be implemented. Control Scope prevents scope creep and ensures changes go through formal change control with impact analysis.

Advanced Project Management — Measuring Project Performance

Move beyond guesswork and status reporting. This course helps you measure real progress, spot problems early, and make confident decisions using proven project performance techniques. If you manage complex projects and want clearer visibility and control, this course is built for you.

This is not abstract theory. You’ll work step by step through Earned Value Management (EVM), learning how cost, schedule, and scope come together to show true performance. You’ll build a solid foundation in EVM concepts, understand why formulas work, and learn how performance data actually supports leadership decisions.

You’ll master Work Breakdown Structures (WBS), control accounts, and budget baselines, then apply core EVM metrics like EAC, TCPI, and variance analysis. Through a detailed real-world example, you’ll forecast outcomes, analyze trends, and understand contingencies and management reserves with confidence.

Learn how experienced project managers monitor performance, communicate results clearly, and take corrective action before projects slip. With practical exercises and hands-on analysis, you’ll be ready to apply EVM immediately. Enroll now and start managing performance with clarity and control.



Launch your Agile career!

HK School of Management helps you master Agile and Scrum—faster. Learn practical playbooks, AI-powered prompts, and real-world workflows to plan smarter, deliver sooner, and keep stakeholders aligned. For the price of lunch, you’ll get templates, tools, and step-by-step guidance to level up your projects. Backed by our 30-day money-back guarantee—zero risk, clear path to results.

Learn More