7.3 Validate Scope
| 7.3 Validate Scope | ||
|---|---|---|
| Inputs | Tools & Techniques | Outputs |
Confirm completed deliverables meet agreed requirements and secure formal acceptance from the customer or sponsor.
Purpose & When to Use
- Gain formal sign-off that deliverables meet agreed requirements and acceptance criteria.
- Reduce rework and disputes by confirming scope completion with the customer or sponsor.
- Used after internal quality checks confirm correctness of the deliverable.
- Performed at the end of a phase, iteration, or when a major deliverable is ready.
- In agile or hybrid work, occurs during reviews or demos where the product owner accepts items.
Mini Flow (How It’s Done)
- Gather inputs: scope baseline, requirements documentation and traceability matrix, acceptance criteria, and verified deliverables.
- Plan the review: schedule the session, invite decision-makers, and prepare evidence such as test results and checklists.
- Run the review or demo: compare the deliverable against acceptance criteria, inspect outputs, and note variances or issues.
- Decide acceptance: approve, approve with minor conditions, or reject and request corrections.
- Record outcomes: obtain formal sign-off if accepted, or log defects and raise change requests if not accepted.
- Update project information: capture acceptance status and issues as work performance information, and record lessons learned.
Quality & Acceptance Checklist
- Deliverable matches the defined scope and acceptance criteria.
- All related requirements in the traceability matrix are satisfied.
- Nonfunctional requirements and constraints are confirmed where applicable.
- Supporting evidence is available, including test results, measurements, and checklists.
- User documentation, training materials, and operating procedures are complete.
- Open defects and risks are documented, owned, and acceptable to the customer.
- Formal acceptance is captured, including signatures, emails, or tickets.
- Configuration item identifiers, versions, and baselines are updated after acceptance.
- Change requests are raised for any new or changed requirements.
Common Mistakes & Exam Traps
- Confusing internal quality checks with customer acceptance; quality control verifies correctness, while validate scope secures formal sign-off.
- Assuming a deliverable is accepted because it passed testing; acceptance requires customer or sponsor approval.
- Skipping the requirements traceability matrix during reviews, which leads to missed criteria.
- Allowing scope changes in the meeting without a change request and approval through change control.
- Gold plating or adding extras not requested, which can be rejected and cause delays.
- Delaying acceptance until project close, increasing risk of late rework.
- Failing to capture objective evidence of acceptance, such as signed forms or system approvals.
- Updating baselines after acceptance without formal configuration control.
PMP Example Question
An internal test team confirms a deliverable meets specifications. What should the project manager do next?
- Update the scope baseline to reflect the completed work.
- Request a customer review to obtain formal acceptance.
- Close the project or phase because testing is complete.
- Issue a change request to release contingency reserves.
Correct Answer: B — Request a customer review to obtain formal acceptance.
Explanation: After internal verification, the next step is to validate scope with the customer or sponsor and capture formal sign-off. Baseline updates and closure come after acceptance, not before.
HKSM