7.10 Monitor Risks

7.10 Monitor Risks
Inputs Tools & Techniques Outputs

Replace this with term.

Purpose & When to Use

Monitor Risks keeps risk information current and actionable. It confirms that planned responses are carried out, checks whether they work, identifies new or changing risks, and triggers issue and change management when needed.

  • Use throughout the project, starting after planning and continuing at a set cadence or when major changes occur.
  • Support proactive decisions on reserves, scope, schedule, cost, and quality based on risk trends and triggers.
  • Provide clear visibility to stakeholders through updated logs, reports, and lessons learned.

Mini Flow (How It’s Done)

  • Prepare: Review the risk management approach, thresholds, latest risk register, response plans, baselines, and performance data.
  • Hold risk reviews: Check early warning indicators and triggers, confirm risk owners have acted, and verify response implementation status.
  • Assess effectiveness: Reevaluate probability, impact, and trends; compare actuals vs. expected outcomes; perform reserve analysis and trend/variance checks.
  • Decide actions: Continue, adjust, or close responses; identify and log residual and secondary risks; escalate risks beyond project authority.
  • Record and communicate: Update the risk register and dashboards; move realized risks to the issue log; submit change requests when baselines or plans must change; share updates with stakeholders.
  • Repeat at cadence: Schedule the next review and maintain watchlists for low-priority risks.

Quality & Acceptance Checklist

  • Risk register updated with current status, dates, triggers, owners, and next review dates.
  • Evidence that planned responses were implemented or formally deferred with rationale.
  • Measured effectiveness recorded, including metrics and trend observations.
  • New, residual, and secondary risks captured with preliminary analysis and ownership.
  • Realized risks transferred to the issue log with actions, due dates, and assignees.
  • Appropriate change requests raised for needed plan or baseline adjustments.
  • Contingency and management reserve usage tracked and forecasts updated.
  • Escalated risks documented with recipients and outcomes.
  • Stakeholder communications sent per the communications approach.
  • Lessons learned for risks and responses captured and shared.

Common Mistakes & Exam Traps

  • Confusing monitoring with implementing responses. Implementing executes the plan; monitoring tracks results and decides adjustments.
  • Treating a realized risk as a “risk.” Once it occurs, manage it as an issue and consider change control if plans must change.
  • Ignoring opportunities. Monitor both threats and opportunities and act on upside triggers.
  • Failing to define or track triggers and early indicators, leading to late reactions.
  • Not engaging risk owners or following up on assigned actions.
  • Changing scope, schedule, or cost without integrated change control.
  • Closing risks too early without evidence that the response worked, or missing secondary risks created by the response.
  • Overreacting to low-priority watchlist items and creating churn instead of following thresholds and cadence.

PMP Example Question

Midway through a project, a threat’s response was implemented, but recent performance data still shows delays tied to that risk. The risk owner says the plan is in place. What should the project manager do next?

  1. Close the risk since the response has been implemented.
  2. Immediately submit a change request to add more schedule buffer.
  3. Conduct a risk review to evaluate response effectiveness, update the risk register, and decide adjustments or new actions.
  4. Escalate to the sponsor and replace the supplier at once.

Correct Answer: C — Conduct a risk review to evaluate response effectiveness, update the risk register, and decide adjustments or new actions.

Explanation: Monitoring verifies whether responses work and updates records. Changes or escalation should follow analysis and the change process, not occur automatically.

Project Management Bootcamp

Embark on a transformative journey with our Project Management Bootcamp at HK School of Management. Elevate from beginner to pro using the latest PMBOK and Process Groups Practice Guide. Our unique, engaging approach makes learning interactive and fun, replacing dull slides with dynamic doodles and real-life scenarios.

This hands-on program includes working on two full project plans. The first evolves as you learn, while the second culminates in a comprehensive plan, solidifying your expertise. You'll navigate real-world challenges, backed by quizzes and in-depth analysis, avoiding common pitfalls and setting you on a path to success.

Enhance your learning with downloadable materials and templates, invaluable for your future projects. The course covers essential topics like PMI, PMO, PMBOK, and project management ethics, delving into critical process groups and key areas such as scope, schedule, cost, and stakeholder management.

Learn from seasoned professionals and join a community of enthusiastic lifelong learners. Ready to master project management and lead with confidence? Enroll now and start your transformation!



Stop Managing Admin. Start Leading the Future!

HK School of Management helps you master AI-Prompt Engineering to automate chaos and drive strategic value. Move beyond status reports and risk logs by turning AI into your most capable assistant. Learn the core elements of prompt engineering to save hours every week and focus on high-value leadership. For the price of lunch, you get practical frameworks to future-proof your career and solve the blank page problem immediately. Backed by a 30-day money-back guarantee-zero risk, real impact.

Enroll Now
``` ### Marketing Notes for this Revision: * **The Hook:** I used the "Stop/Start" phrasing from your landing page description because it creates a clear transformation for the user. * **The Value:** It highlights the specific pain point mentioned in your text (drowning in administrative work) and offers the "AI Assistant" model as the solution. * **The Pricing/Risk:** I kept the "price of lunch" and "guarantee" messaging as it is a powerful way to reduce friction for a Udemy course. Would you like me to create a second version that focuses more specifically on the "fear of obsolescence" mentioned in your landing page info?