Close Project or Phase

Governance/Closing/Close Project or Phase
Inputs Tools & Techniques Outputs

Inputs, tools & techniques, and outputs for this process.

A structured wrap-up that confirms deliverables are accepted, finishes contracts and finances, hands off outcomes to operations, captures lessons learned, updates records, and releases resources to formally end a project or phase.

Purpose & When to Use

This activity brings formal closure to a project or phase. It verifies completion against agreed acceptance criteria, obtains sign-off, transitions deliverables to operations or the next phase, and preserves knowledge for future work. It supports value delivery by ensuring benefits ownership and operational readiness are in place.

  • Confirm scope is complete and accepted by authorized stakeholders.
  • Transition deliverables to operations, support, or the next phase.
  • Close procurements and financials, and release resources.
  • Capture lessons learned and archive records for reuse.
  • Communicate final results, performance, and benefits readiness.

Use this at the end of every phase and at final project completion, including early termination or cancellation.

Mini Flow (How It’s Done)

  • Review the project management plan and closure checklist tailored to the delivery approach (predictive, agile, hybrid).
  • Verify that all requirements and deliverables meet acceptance criteria; address any outstanding defects or concessions.
  • Obtain formal acceptance and sign-off from the sponsor or authorized customer representative.
  • Complete procurements: settle claims, process final invoices, obtain release of liabilities, and document contract closure.
  • Transition to operations: deliver handover documents, training, support plans, warranties, and access credentials.
  • Close financials: reconcile costs, release remaining funds, account for assets, and update final forecasts and benefits baseline.
  • Capture lessons learned through a retrospective; document what to keep, what to change, and why.
  • Update repositories: requirements traceability, configuration records, test evidence, approvals, and final baseline.
  • Release team members and other resources; complete performance feedback and administrative closeout.
  • Issue a final report summarizing scope, schedule, cost, quality, risks, benefits readiness, and outstanding follow-up actions.

Quality & Acceptance Checklist

  • All deliverables verified against criteria and defects resolved or formally waived.
  • Formal acceptance/sign-off recorded by the authorized stakeholder.
  • Requirements traceability matrix shows complete status and final disposition for each requirement.
  • Configuration items updated; final versions and baselines are stored and accessible.
  • Test results, quality records, and compliance evidence archived.
  • Operational readiness confirmed: procedures, training, support model, SLAs, and contact points in place.
  • Data migration or cutover executed and validated, with rollback outcomes documented.
  • Contracts closed: final payments made, claims settled, and closeout certificates filed.
  • Financial closure complete: budgets reconciled, assets recorded, and remaining funds released.
  • Risks and issues closed or formally transferred with owners and due dates.
  • Lessons learned captured, shared, and indexed for search in the knowledge base.
  • Stakeholders notified of closure; final report and archives communicated and stored.

Common Mistakes & Exam Traps

  • Skipping formal acceptance; always get documented sign-off from the authorized person.
  • Releasing the team before closing procurements and financials.
  • Treating closure as paperwork only; ensure a real operational handover and support readiness.
  • Leaving change requests, defects, or claims unresolved; decide, defer with agreement, or close them.
  • Confusing phase closure with project closure; in phase closure, only the phase is closed and resources may continue into the next phase.
  • Failing to transfer benefits measurement and ownership to the appropriate operational owner.
  • Not updating configuration records and repositories, causing future support gaps.
  • Ignoring early-termination steps; canceled projects still require full closure activities.
  • For adaptive approaches, forgetting to document the status of remaining backlog items and transition plans.

PMP Example Question

A project’s deliverables are accepted by the customer, but a vendor has a small unresolved claim. What should the project manager do next before releasing the team?

  1. Release the team and let procurement handle the claim separately.
  2. Archive documents and close the project since acceptance is complete.
  3. Work with procurement to settle the claim and complete contract closure, then finish project closure activities.
  4. Ignore the claim because it is minor and proceed with closure.

Correct Answer: C — Work with procurement to settle the claim and complete contract closure, then finish project closure activities.

Explanation: All procurements must be closed and claims resolved or formally settled before releasing resources and completing project closure.

AI-Prompt Engineering for Strategic Leaders

Stop managing administration and start leading the future. This course is built specifically for managers and project professionals who want to automate chaos and drive strategic value using the power of artificial intelligence.

We don't teach you how to program Python; we teach you how to program productivity. You will master the AI-First Mindset and the 'AI Assistant' model to hand off repetitive work like status reports and meeting minutes so you can focus on what humans do best: empathy, negotiation, and vision.

Learn the 5 Core Prompt Elements-Role, Goal, Context, Constraints, and Output-to get high-quality results every time. You will build chained sequences for complex tasks like auditing schedules or simulating risks, while navigating ethics and privacy with human-in-the-loop safeguards.

Move from being an administrative manager to a high-value strategic leader. Future-proof your career today with practical, management-focused AI workflows that map to your real-world challenges. Enroll now and master the language of the future.



Become an AI-First Agile Leader!

HK School of Management empowers you to master AI as your most powerful co-pilot—without the complexity. Transform your agile leadership with practical, prompt-based workflows and proven strategies designed for real-world scrum challenges. For the price of lunch, you get the tools to automate mundane tasks, refine backlogs with precision, and drive unprecedented efficiency in your team. Backed by our 30-day money-back guarantee—zero risk, real impact.

Learn More