Physical resource assignments

A documented allocation of non-human tangible resources such as equipment, materials, facilities, and supplies to specific activities, time frames, and locations. It clarifies quantities, availability windows, and responsibilities so the team can plan, execute, and control resource use.

Key Points

  • Focuses on non-human tangible resources such as equipment, materials, facilities, and supplies.
  • Links each resource to activities, dates, locations, quantities, and responsible parties.
  • Used to validate feasibility, coordinate logistics, and prevent over-allocations or shortages.
  • Should note constraints, assumptions, maintenance windows, and fallback options.
  • Kept current through change control and aligned with the schedule and resource calendars.
  • Distinct from team assignments, which cover people and roles.

Purpose of Analysis

  • Confirm that assigned physical resources are sufficient, available, and aligned with the schedule.
  • Detect conflicts, gaps, and double-bookings before they impact delivery.
  • Assess logistics, lead times, and readiness at the point of use.
  • Identify cost, safety, and compliance implications related to resource use.

Method Steps

  1. Compile current assignments and baselines from the resource management plan, schedule, and procurement records.
  2. Map each resource to activities by date, duration, location, and required quantity or capacity.
  3. Check availability calendars, delivery dates, maintenance intervals, and storage constraints.
  4. Compare demand vs. capacity to find shortages, over-allocations, and idle time.
  5. Evaluate logistics and handoffs, including setup, transport, calibration, and teardown time.
  6. Assess risks and constraints; note dependencies, safety, and compliance requirements.
  7. Develop options: reschedule, split quantities, substitute equivalents, rent, or add buffer stock.
  8. Review options with stakeholders, submit necessary change requests, and update plans and registers.
  9. Communicate updates to the team and suppliers, and monitor through regular reviews.

Inputs Needed

  • Resource management plan and resource calendars.
  • Project schedule with activity resource requirements.
  • Bills of materials, specifications, and quality standards.
  • Procurement plans, contracts, delivery schedules, and supplier commitments.
  • Inventory levels, storage limits, and handling constraints.
  • Risk register, assumptions log, and constraints.
  • Site access rules, safety requirements, and compliance guidelines.

Outputs Produced

  • Updated physical resource assignment list or matrix with dates, quantities, and locations.
  • Resource usage charts or heat maps showing peaks and conflicts.
  • Issue and gap log with recommended actions and owners.
  • Change requests for schedule, procurement, or scope adjustments.
  • Updated delivery and logistics plan, risk register, and communications.

Interpretation Tips

  • Prioritize conflicts that affect critical path activities and regulatory milestones.
  • Verify that setup and transport time do not hide behind task durations.
  • Cross-check lead times and minimum order quantities against activity need dates.
  • Watch for shared equipment used across projects that may not appear in one schedule.
  • Use simple visuals to expose spikes in demand and idle capacity.
  • Confirm on-site readiness: space, power, permits, and safety measures.

Example

A project plans to use a thermal chamber for qualification testing in Week 6 and Week 7. Analysis of physical resource assignments shows the chamber is booked for preventive maintenance in Week 6 and that shipment of specialized fixtures arrives only in Week 7. The team reschedules testing to start in Week 7, rents a backup chamber for surge capacity in Week 8, and updates the assignment matrix and risk register.

Pitfalls

  • Treating assignments as static and not updating them after schedule or procurement changes.
  • Ignoring setup, calibration, transport, and teardown time when planning availability.
  • Overlooking consumables, spare parts, or tooling required to use the primary equipment.
  • Assuming supplier delivery dates are firm without confirmed commitments.
  • Failing to note unit conversions or quantity breaks that affect availability and cost.
  • Not documenting assumptions and fallback options for critical resources.

PMP Example Question

During execution, two parallel activities require the same specialized test rig that is listed as assigned to both during the same week. What should the project manager do first?

  1. Update the risk register to add a new risk and proceed with the plan.
  2. Analyze physical resource assignments against the schedule to confirm the conflict and evaluate options.
  3. Submit a change request to compress the schedule so the conflict disappears.
  4. Rent another test rig immediately to avoid delays.

Correct Answer: B — Analyze physical resource assignments against the schedule to confirm the conflict and evaluate options.

Explanation: The first step is to validate and analyze the conflict using current assignments and the schedule, then select and route an appropriate corrective action through change control if needed.

Project Management Bootcamp

Embark on a transformative journey with our Project Management Bootcamp at HK School of Management. Elevate from beginner to pro using the latest PMBOK and Process Groups Practice Guide. Our unique, engaging approach makes learning interactive and fun, replacing dull slides with dynamic doodles and real-life scenarios.

This hands-on program includes working on two full project plans. The first evolves as you learn, while the second culminates in a comprehensive plan, solidifying your expertise. You'll navigate real-world challenges, backed by quizzes and in-depth analysis, avoiding common pitfalls and setting you on a path to success.

Enhance your learning with downloadable materials and templates, invaluable for your future projects. The course covers essential topics like PMI, PMO, PMBOK, and project management ethics, delving into critical process groups and key areas such as scope, schedule, cost, and stakeholder management.

Learn from seasoned professionals and join a community of enthusiastic lifelong learners. Ready to master project management and lead with confidence? Enroll now and start your transformation!



Launch your career!

HK School of Management provides world-class training in Project Management, Lean Six Sigma, and Agile Methodologies. Just for the price of a lunch you can transform your career, and reach new heights. With 30 days money-back guarantee, there is no risk.

Learn More