Cost management

Cost management is the structured approach to estimating, budgeting, funding, monitoring, and controlling project costs so work is delivered within the approved budget. It supports informed decisions about trade-offs and financial transparency across the project life cycle.

Key Points

  • Cost management aligns with scope and schedule to create a time-phased cost baseline for control.
  • Estimation uses methods like analogous, parametric, bottom-up, and three-point to balance speed and accuracy.
  • Reserves are planned and visible: contingency for identified risks and management reserve for unforeseen events.
  • Performance is tracked with measures such as PV, EV, AC and indicators like CPI and SPI to assess variance.
  • Forecasts such as EAC and ETC guide corrective actions and funding decisions.
  • Changes to the cost baseline go through integrated change control with clear impacts on scope and schedule.

Purpose of Analysis

  • Establish a realistic budget and funding profile that supports delivery objectives.
  • Quantify cost risk and set appropriate reserves to protect the baseline.
  • Identify cost drivers and trade-offs to optimize scope, schedule, and resources.
  • Detect variances early and forecast outcomes to enable timely corrective actions.
  • Provide transparent, decision-ready information for sponsors and stakeholders.

Method Steps

  • Define cost structure: set cost categories, coding, and WBS-based aggregation rules.
  • Estimate costs: select techniques (analogous, parametric, bottom-up, three-point) and quantify assumptions.
  • Incorporate risks: translate key risks into cost impacts and set contingency and management reserve policies.
  • Build the budget: time-phase estimates to the schedule to form the cost baseline and funding requirements.
  • Plan control: choose metrics, thresholds, reporting cadence, and EVM rules of credit.
  • Monitor and control: track actuals, analyze variances, update forecasts (EAC/ETC), and propose changes when needed.

Inputs Needed

  • Scope baseline, WBS, and acceptance criteria.
  • Schedule, resource plan, and resource rates or labor calendars.
  • Risk register with cost-related risks and response strategies.
  • Historical data, benchmarks, and organizational estimating policies.
  • Vendor quotes, contract terms, and procurement strategy.
  • Financial constraints, funding limits, and accounting rules.

Outputs Produced

  • Cost management plan with estimation, budgeting, and control approaches.
  • Time-phased cost baseline and overall project budget.
  • Funding requirements and cash flow profile.
  • Defined reserves: contingency and management reserve policies.
  • Performance reports, variance analyses, and EAC/ETC forecasts.
  • Change requests and recommendations for corrective or preventive actions.

Interpretation Tips

  • Look at CPI and SPI together; cost and schedule issues often share root causes.
  • Check burn rate and cash flow timing to avoid funding shortfalls even when within budget.
  • Validate variances against thresholds before escalating; investigate causes before prescribing fixes.
  • Use ranges and confidence levels; avoid false precision in early estimates.
  • Translate technical variances into business impact to support decision-making.

Example

A project has a time-phased baseline of 1.2M over 12 months. At month 6, EV is 480k, AC is 600k, and PV is 540k. CPI = 0.80 and SPI = 0.89 indicate cost overrun and delay.

  • The team reviews cost drivers: overtime, rework, and a vendor price increase.
  • They update EAC using a CPI-based forecast and model alternative scenarios with corrective actions.
  • A change request is raised to implement process improvements and re-negotiate the vendor contract, with an updated forecast and risk-adjusted reserve.

Pitfalls

  • Ignoring risk in estimates, leading to inadequate contingency reserves.
  • Rebaselining without cause analysis, masking performance issues.
  • Focusing on total budget but neglecting cash flow and funding constraints.
  • Overreliance on a single estimating method or outdated rates.
  • Poor rules of credit, causing misleading EVM metrics.
  • Weak integration with change control and procurement, creating hidden cost creep.

PMP Example Question

Midway through a project, EV = 400k, AC = 500k, and PV = 450k. What should the project manager do next?

  1. Request additional funding from the sponsor to cover the overrun.
  2. Perform variance analysis, update EAC/ETC forecasts, and recommend corrective actions.
  3. Rebaseline the project immediately to reflect current performance.
  4. Crash the schedule to recover the CPI and SPI.

Correct Answer: B — Perform variance analysis, update EAC/ETC forecasts, and recommend corrective actions.

Explanation: CPI and SPI are below 1, indicating cost and schedule issues. The appropriate next step is to analyze root causes, forecast outcomes, and propose actions through change control before seeking more funds or rebaselining.

How To Land the Job and Interview for Project Managers Course

Take the next big step in your project management career with HK School of Management. Whether you're breaking into the field or aiming for your dream job, this course gives you the tools to stand out, impress in interviews, and secure the role you deserve.

This isn’t just another job-hunting guide—it’s a tailored roadmap for project managers. You’ll craft winning resumes, tackle tough interview questions, and plan your first 90 days with confidence. Our hands-on approach includes real-world examples, AI-powered resume hacks, and interactive exercises to sharpen your skills.

You'll navigate the hiring process like a pro, with expert insights on personal branding, salary negotiation, and career growth strategies. Plus, downloadable templates and step-by-step guidance ensure you're always prepared.

Learn from seasoned professionals and join a community of ambitious project managers. Ready to land your ideal job and thrive in your career? Enroll now and take control of your future!



Launch your career!

HK School of Management delivers top-tier training in Project Management, Job Search Strategies, and Career Growth. For the price of a lunch, you’ll gain expert insights into landing your dream PM role, mastering interviews, and negotiating like a pro. With a 30-day money-back guarantee, there’s zero risk—just a clear path to success!

Learn More