complete performance index

A forecasting measure in earned value management that shows the cost efficiency needed on the remaining work to meet a budget target. It compares remaining work to remaining funds and is often referred to as the to-complete performance index (TCPI).

Key Points

  • Also called the to-complete performance index (TCPI); it focuses on future cost efficiency.
  • Calculated as remaining work divided by remaining funds against a chosen target (BAC or EAC).
  • Use BAC when aiming to meet the original budget; use EAC when a new forecast is the agreed target.
  • Interpretation: greater than 1.0 means tougher to achieve, equal to 1.0 means on-plan, less than 1.0 means favorable.
  • Compare the required efficiency to current CPI to judge feasibility and need for corrective action.
  • Based on the same status date and consistent EV data to avoid misleading results.

Purpose of Analysis

  • Assess how efficiently the team must perform on remaining work to hit a cost target.
  • Support decisions on corrective actions, replanning, or accepting a revised forecast.
  • Communicate whether the current performance trend is sufficient to meet objectives.

Method Steps

  • Confirm the status date and ensure EV data is current and consistent.
  • Gather BAC, EV, AC, and the latest approved EAC if applicable.
  • Choose the target: original budget at completion (BAC) or revised estimate at completion (EAC).
  • Compute: for BAC target, (BAC − EV) ÷ (BAC − AC); for EAC target, (BAC − EV) ÷ (EAC − AC).
  • Compare the result to current CPI and evaluate realism based on team capacity and constraints.
  • Decide actions such as cost controls, scope trade-offs, resource changes, or accepting a new EAC.

Inputs Needed

  • BAC - Budget at Completion.
  • EV - Earned Value as of the status date.
  • AC - Actual Cost as of the status date.
  • EAC - Estimate at Completion, if using a revised target.
  • Status date and any approved changes affecting scope or budget.

Outputs Produced

  • The required cost efficiency index to meet BAC or EAC.
  • Feasibility assessment when compared to current CPI and trends.
  • Recommended corrective or preventive actions.
  • Updated forecasts or management communications, as needed.

Interpretation Tips

  • Greater than 1.0 means the team must perform more efficiently than the average cost performance to date.
  • Less than 1.0 means the target is easier than current performance and has some buffer.
  • If the required index is significantly higher than historical CPI, consider revising scope, resources, or accepting a new EAC.
  • Use BAC when management insists on the original budget; use EAC when a realistic, approved forecast replaces BAC.
  • Do not interpret in isolation; review CPI, SPI, risks, and funding constraints.

Example

  • Given: BAC = 1,000, EV = 400, AC = 500.
  • To meet BAC: TCPI = (BAC − EV) ÷ (BAC − AC) = (1,000 − 400) ÷ (1,000 − 500) = 600 ÷ 500 = 1.20.
  • If EAC = 1,100, to meet EAC: TCPI = (1,000 − 400) ÷ (1,100 − 500) = 600 ÷ 600 = 1.00.
  • Interpretation: Hitting the original BAC needs a 1.20 efficiency going forward, which may be challenging; meeting the approved EAC needs 1.00, which is more realistic.

Pitfalls

  • Using the wrong target baseline (mixing BAC and EAC) for the calculation.
  • Comparing TCPI to CPI from a different status date or with inconsistent EV data.
  • Assuming a high TCPI is achievable without checking capacity, constraints, or risks.
  • Ignoring the need to update EAC when repeated high TCPI values are unrealistic.
  • Focusing only on the index and overlooking schedule or scope drivers of cost.

PMP Example Question

A project has BAC = 900, EV = 360, AC = 450, and an approved EAC of 1,000. What does the complete performance index to meet the approved EAC indicate?

  1. TCPI = 1.20, performance must improve significantly.
  2. TCPI = 0.90, performance can be slightly lower than current.
  3. TCPI = 1.00, performance must match plan going forward.
  4. TCPI = 0.80, substantial buffer exists for remaining work.

Correct Answer: C - TCPI = 1.00, performance must match plan going forward.

Explanation: For EAC target: (BAC − EV) ÷ (EAC − AC) = (900 − 360) ÷ (1,000 − 450) = 540 ÷ 550 ≈ 0.98, effectively 1.00. The team needs on-plan cost efficiency for the remaining work.

AI for Agile Project Managers and Scrum Masters

Become an AI-first leader and transform your agile practice by leveraging artificial intelligence as your most powerful co-pilot. This course is designed to help you drive efficiency, insight, and innovation, ensuring you stay at the forefront of a rapidly evolving project management landscape.

This isn't about replacing human intuition—it's about augmenting it. You'll master prompt engineering to automate mundane tasks, freeing up your time for high-impact strategic leadership and creative problem-solving. Learn to refine backlogs, create strategic roadmaps, and integrate AI seamlessly into your agile ceremonies.

Gain predictive power by using AI-driven insights to anticipate project risks and seize new opportunities for more reliable outcomes. We deliver practical, prompt-based workflows and proven strategies built around real-world agile challenges that you can implement immediately within your framework.

Master foundational AI concepts specifically relevant to Scrum environments while developing advanced skills to handle diverse agile scenarios. You will learn to champion an AI-enabled culture within your organization, fostering a dynamic environment of continuous improvement and superior team delivery.

Ready to lead the future of agile and make data-driven decisions that cut through complexity? Join a community of forward-thinking professionals and position yourself as an indispensable leader in the AI era. Enroll now and unlock your future!



Launch your Agile career!

HK School of Management helps you master Agile and Scrum—faster. Learn practical playbooks, AI-powered prompts, and real-world workflows to plan smarter, deliver sooner, and keep stakeholders aligned. For the price of lunch, you’ll get templates, tools, and step-by-step guidance to level up your projects. Backed by our 30-day money-back guarantee—zero risk, clear path to results.

Learn More