Chapter 18
Cost Variance (CV) is calculated as Earned Value (EV) minus Actual Cost (AC). A positive CV indicates the project is under budget, while a negative CV suggests it's over budget. Schedule Variance (SV) is calculated as EV minus Planned Value (PV). A positive SV shows the project is ahead of schedule, and a negative SV means it’s behind schedule.
The Cost Performance Index (CPI) is the ratio of EV to AC and reflects cost efficiency—values above 1 indicate the project is under budget, while values below 1 suggest it’s over budget. The Schedule Performance Index (SPI) is the ratio of EV to PV, showing schedule efficiency. An SPI greater than 1 indicates the project is ahead of schedule, while less than 1 means it’s behind.
Estimate at Completion (EAC) predicts the total cost of a project at completion, based on current performance. It is important for forecasting future budget requirements and ensuring the project stays within financial constraints. One common way to calculate EAC is by using the formula: EAC = Budget at Completion (BAC) divided by Cost Performance Index (CPI).
If EVM metrics show a project is over budget and behind schedule, corrective actions may include revising the project plan, reallocating resources, adjusting the scope, or modifying timelines. It’s crucial to identify root causes and implement strategies to optimize performance and bring the project back on track.
In a past project, EVM revealed significant cost overruns early in the process. Using this insight, I made the decision to reallocate resources and reprioritize tasks. This corrective action helped address the cost issues, and the project was completed on time and within budget, avoiding further delays and financial impact.
The project is over budget (CPI < 1) and behind schedule (SPI < 1). This indicates that the project is spending more than planned for the work completed and is progressing slower than expected.
The project is under budget (CPI > 1) but slightly behind schedule (SPI < 1). This suggests cost efficiency but slower-than-planned progress.
The project is on budget (CPI = 1) and ahead of schedule (SPI > 1). This indicates that the work is progressing faster than planned without exceeding the budget.
Understanding Earned Value Management (EVM), along with project finances and accounting, is crucial. If you’re unable to discuss these concepts confidently in an interview, it’s important to address this knowledge gap. You need to have a solid grasp of project accounting principles, as EVM is just one tool in a larger framework. If you recognize this as a weakness, I highly recommend taking the time to improve your understanding.
Visit our website blog and reed free articles on EVM that you can use to enhance your knowledge. Additionally, we offer a comprehensive advanced project management course. If those options don’t work for you, consider exploring project accounting or advanced project management courses at a college or university you prefer.
Ship value sooner, cut busywork, and lead with confidence. Whether you’re new to Agile or scaling multiple teams, this course gives you a practical system to plan smarter, execute faster, and keep stakeholders aligned.
This isn’t theory—it’s a hands-on playbook for modern delivery. You’ll master Scrum roles, events, and artifacts; turn vision into a living roadmap; and use AI to refine backlogs, write clear user stories and acceptance criteria, forecast with velocity, and automate status updates and reports.
You’ll learn estimation, capacity and release planning, quality and risk management (including risk burndown), and Agile-friendly EVM—plus how to scale with Scrum of Scrums, LeSS, SAFe, and more. Downloadable templates and ready-to-use GPT prompts help you apply everything immediately.
Learn proven patterns from real projects and adopt workflows that reduce meetings, improve visibility, and boost throughput. Ready to level up your delivery and lead in the AI era? Enroll now and start building smarter sprints.
Explore the CourseHK School of Management helps you learn AI prompt engineering for project work. Move beyond status reports and risk logs with practical prompt frameworks for everyday tasks. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.
Enroll NowUnlimited redemptions
Available until September 19, 2026 6:21 PM PDT
2A2133BF88C8DF36C1AA