Variance Analysis
A method used to identify why results differ from the baseline and to measure how large those differences are.
Key Points
- Compares actual results to baseline plans for cost, schedule, and other performance areas.
- Quantifies the size of the deviation and investigates root causes.
- Supports corrective and preventive actions and informs forecasts (for example, EAC in EVM).
- Performed during monitoring and controlling, often alongside trend and earned value analysis.
Example
At the end of month 3, the project planned value is USD 300,000, earned value is USD 250,000, and actual cost is USD 280,000. Variance analysis shows SV = -50,000 and CV = -30,000. The team traces the cause to a vendor delay and overtime costs, then updates the schedule and cost forecasts and implements corrective actions.
PMP Example Question
During Control Costs, the project manager sees that actual costs are higher than planned. Which technique should be used to determine why the deviation occurred and how large it is compared to the baseline?
- Trend analysis
- Variance analysis
- What-if scenario analysis
- Reserve analysis
Correct Answer: B — analyzing differences from the plan and their causes
Explanation: Variance analysis compares actuals to the baseline to quantify the gap and identify root causes, enabling targeted corrective action.