Resource Optimization Technique
A scheduling approach that shifts activity start and finish dates so resource demand fits the available capacity, typically through methods such as resource leveling and resource smoothing.
Key Points
- Balances resource demand with actual availability to remove over-allocation.
- Common methods include resource leveling (may extend the schedule) and resource smoothing (keeps the end date by using float).
- Can affect the critical path and total project duration, depending on the method used.
- Applied iteratively during schedule development and control using resource calendars and constraints.
Example
A construction project has one crane available. The PM staggers steel placement activities so only one task needs the crane at a time. Noncritical tasks are moved within their float (smoothing); if conflicts remain, some tasks are pushed beyond float, extending the schedule (leveling).
PMP Example Question
A project manager adjusts several activities' start and finish dates so no team member or key tool is over-allocated relative to what is available. What technique is being applied?
- Crashing
- Resource optimization
- Fast tracking
- Bottom-up estimating
Correct Answer: B — Resource optimization technique
Explanation: Resource optimization modifies activity timing to match resource demand to available supply, typically using leveling or smoothing. It is not schedule compression (crashing or fast tracking) or an estimating method.