Resource Optimization Technique
A scheduling approach that shifts activity start and finish dates so resource demand fits the available capacity, typically through methods such as resource leveling and resource smoothing.
Key Points
- Balances resource demand with actual availability to remove over-allocation.
- Common methods include resource leveling (may extend the schedule) and resource smoothing (keeps the end date by using float).
- Can affect the critical path and total project duration, depending on the method used.
- Applied iteratively during schedule development and control using resource calendars and constraints.
Example
A construction project has one crane available. The PM staggers steel placement activities so only one task needs the crane at a time. Noncritical tasks are moved within their float (smoothing); if conflicts remain, some tasks are pushed beyond float, extending the schedule (leveling).
PMP Example Question
A project manager adjusts several activities' start and finish dates so no team member or key tool is over-allocated relative to what is available. What technique is being applied?
- Crashing
- Resource optimization
- Fast tracking
- Bottom-up estimating
Correct Answer: B — Resource optimization technique
Explanation: Resource optimization modifies activity timing to match resource demand to available supply, typically using leveling or smoothing. It is not schedule compression (crashing or fast tracking) or an estimating method.
HKSM