Float

The amount of schedule flexibility for an activity or path, expressed as how long it can be delayed without creating a defined impact. In practice, this flexibility is measured as total float when the impact is the project finish date, or as free float when the impact is the start of the immediate successor.

Key Points

  • Also called slack. See total float and free float.
  • Calculated via critical path method by comparing early and late dates from forward and backward passes.
  • Activities on the critical path typically have zero total float; negative float indicates a schedule that violates an imposed date.
  • Float is consumable and can be reduced by changes, risk responses, or resource leveling, so it should be monitored and managed.

Example

In a sequence A -> B -> C, B is planned to finish on day 6 and C is scheduled to start on day 9. B can slip to finish as late as day 9 without delaying C, so B has 3 days of free float. If the project finish depends on C, B also has 3 days of total float.

PMP Example Question

Which statement best describes float in a project schedule?

  1. The budget reserve available to absorb cost overruns.
  2. The time an activity can slip before affecting a defined schedule date, such as the project finish or a successor's start.
  3. The difference between optimistic and pessimistic duration estimates.
  4. Idle time caused by resource underutilization.

Correct Answer: B — time an activity can slip before affecting a specified schedule date

Explanation: Float represents schedule flexibility; common forms are total float (relative to project finish) and free float (relative to the successor's start).

ICS/OT Incident Response Plan: Write One That Works

Most OT incident response plans fail before anyone writes a word: no sponsor, no charter, no agreement on who decides. This workshop course takes you from a blank page to a plan your site approves and your operators can follow.

Each of the eight sections writes one chapter of your plan: the authority and scope, the inputs, severity in the language of the plant, command and decision rights, response steps, recovery and the readiness library.

You get the plan template, more than 40 templates and worksheets, 21 worked examples and a capstone with a full model answer.

50 videos, 7.7 hours. US$147 one-time through HKSM Courses. 30-day money-back guarantee when 50% or less consumed.

Explore the Course


ICS/OT Incident Response Plan course preview

Take Control of Project Performance!

HK School of Management and Technology helps you go beyond status reports and gut feelings. In this advanced course, you will learn Earned Value Management (EVM) to measure progress, forecast outcomes, and take corrective action. Learn how WBS quality drives performance, how control accounts work, and how to use EAC, TCPI, and variance analysis. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Learn More