Float

The amount of schedule flexibility for an activity or path, expressed as how long it can be delayed without creating a defined impact. In practice, this flexibility is measured as total float when the impact is the project finish date, or as free float when the impact is the start of the immediate successor.

Key Points

  • Also called slack. See total float and free float.
  • Calculated via critical path method by comparing early and late dates from forward and backward passes.
  • Activities on the critical path typically have zero total float; negative float indicates a schedule that violates an imposed date.
  • Float is consumable and can be reduced by changes, risk responses, or resource leveling, so it should be monitored and managed.

Example

In a sequence A -> B -> C, B is planned to finish on day 6 and C is scheduled to start on day 9. B can slip to finish as late as day 9 without delaying C, so B has 3 days of free float. If the project finish depends on C, B also has 3 days of total float.

PMP Example Question

Which statement best describes float in a project schedule?

  1. The budget reserve available to absorb cost overruns.
  2. The time an activity can slip before affecting a defined schedule date, such as the project finish or a successor's start.
  3. The difference between optimistic and pessimistic duration estimates.
  4. Idle time caused by resource underutilization.

Correct Answer: B — time an activity can slip before affecting a specified schedule date

Explanation: Float represents schedule flexibility; common forms are total float (relative to project finish) and free float (relative to the successor's start).

Leadership for Project Managers Course

Lead with clarity, confidence, and real impact. This Leadership for Project Managers course turns day-to-day challenges—unclear priorities, tough stakeholders, and cross-functional friction—into opportunities to guide teams and deliver outcomes that matter.

You’ll learn practical leadership skills tailored to project realities: setting direction without overcontrol, creating alignment across functions, and building commitment even when authority is limited. We go beyond theory with tools you can use immediately—one-sentence visioning, stakeholder influence maps, decision framing, and feedback scripts that actually land.

Expect hands-on frameworks, real-world examples, and guided practice to prepare for tough moments—executive readouts, resistance from stakeholders, and high-stakes negotiations. Downloadable templates and checklists keep everything actionable when the pace gets intense.

Learn alongside professionals around the world working in project leadership and delivery.

Explore the Course


Launch your career!

HK School of Management offers training in project management, job-search strategies, and career growth. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Learn More