Estimate at Completion (EAC)

The projected total cost to finish all project work, found by adding the actual cost incurred to date (AC) to the estimated cost needed to complete the remaining work (ETC).

Key Points

  • Estimate at Completion (EAC) forecasts what the project will cost when all work is done.
  • Base formula: EAC = AC + ETC, especially when a fresh, bottom-up ETC is prepared.
  • Common EVM variants include: EAC = AC + (BAC - EV)/CPI, EAC = BAC/CPI, and EAC = AC + (BAC - EV)/(CPI*SPI) depending on assumptions.
  • Related terms: BAC (original total budget), ETC (remaining cost), VAC = BAC - EAC (expected overrun/underrun).

Example

A project has AC = $900,000 at mid-point. The team re-estimates the remaining work (ETC) at $1,300,000. EAC = AC + ETC = $900,000 + $1,300,000 = $2,200,000. If BAC was $2,000,000, then VAC = $2,000,000 - $2,200,000 = -$200,000 (project is forecast to finish $200,000 over budget).

PMP Example Question

A project reports AC = $700k, EV = $600k, BAC = $1.2M, and CPI = 0.75. If you assume the remaining work will continue at the current cost performance, what is the Estimate at Completion?

  1. $1,500,000
  2. $1,600,000
  3. $1,300,000
  4. $500,000

Correct Answer: A — EAC (total forecast cost) using CPI-based formula

Explanation: With performance expected to continue, EAC = AC + (BAC - EV)/CPI = 700,000 + (1,200,000 - 600,000)/0.75 = 700,000 + 800,000 = 1,500,000.

ICS/OT Incident Drills and Tabletop Exercises

An incident response plan is only a theory until the people who must use it have run it under pressure. This course helps OT engineers, operations leaders, IT responders, and security teams turn a plan on paper into a tested capability.

Define safe states and manual fallback before an incident forces the decision. Build escalation paths, tabletop exercises, and scenarios that expose the gaps a document review cannot find.

Then turn the results into evidence: an after-action report, owned improvements, recovery checks, and a drill cadence that keeps the program alive after the exercise ends.

51 lessons, 4.8 hours of video, eight quizzes and four hands-on assignments. US$47 one-time through HKSM Courses. 30-day money-back guarantee when 50% or less consumed.

Explore the Course


ICS/OT Incident Drills and Tabletop Exercises course preview

Lead with clarity, influence, and outcomes.

HK School of Management and Technology offers a practical Leadership for Project Managers course for real projects, tight deadlines, and cross-functional teams. Learn to set direction, align stakeholders, and drive commitment without relying on title. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Learn More