Cost Variance (CV)

At a specific point in time, the difference between earned value (EV) and actual cost (AC), indicating whether the project has a budget surplus or shortfall.

Key Points

  • Formula: CV = EV - AC.
  • CV > 0 means under budget (surplus); CV < 0 means over budget (deficit); CV = 0 means on budget.
  • Reported at a point in time as part of earned value management (EVM).
  • Used with CPI, SV, and trend analysis to assess performance and refine forecasts like EAC/ETC.

Example

At the end of month 4, EV = $400,000 and AC = $450,000. CV = EV - AC = $400,000 - $450,000 = -$50,000, indicating the project is over budget by $50,000.

PMP Example Question

A project at month 3 reports EV = $120,000 and AC = $135,000. What is the cost variance and what does it mean?

  1. $15,000; the project is over budget
  2. -$15,000; the project is over budget
  3. -$15,000; the project is under budget
  4. $15,000; the project is under budget

Correct Answer: B - Negative $15,000 cost variance indicates over budget

Explanation: CV = EV - AC = 120,000 - 135,000 = -15,000. A negative CV means actual spending exceeds the earned value, so the project is over budget.

Leadership for Project Managers Course

Lead with clarity, confidence, and real impact. This Leadership for Project Managers course turns day-to-day challenges—unclear priorities, tough stakeholders, and cross-functional friction—into opportunities to guide teams and deliver outcomes that matter.

You’ll learn practical leadership skills tailored to project realities: setting direction without overcontrol, creating alignment across functions, and building commitment even when authority is limited. We go beyond theory with tools you can use immediately—one-sentence visioning, stakeholder influence maps, decision framing, and feedback scripts that actually land.

Expect hands-on frameworks, real-world examples, and guided practice to prepare for tough moments—executive readouts, resistance from stakeholders, and high-stakes negotiations. Downloadable templates and checklists keep everything actionable when the pace gets intense.

Learn alongside professionals around the world working in project leadership and delivery.

Explore the Course


Advance your Lean Six Sigma expertise!

HK School of Management and Technology helps you take Lean Six Sigma to the next level without the overwhelm. Master advanced statistical tools, Excel-based analysis, and real-world improvement techniques to solve complex problems with confidence. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Learn More